|
|
Canadian Historic Sites: Occasional Papers in Archaeology and History No. 17
The Halifax Citadel, 1825-60: A Narrative and Structural History
by John Joseph Greenough
Appendix G: Walls
The Escarps
Of all the individual features of the Citadel, the escarp walls
caused the most grief. Designed to inadequate specifications, they were,
from the first, likely to collapse. They were redesigned several times
and were not entirely completed until the mid-1840s. Even then,
substantial portions of the escarp wall were of dubious quality, and
remained problematical right down to the completion of the work and
beyond.
The origin of the problem is discussed more fully in the main part of
this report. It should suffice to say that Colonel Nicolls proposed
escarps of a thin profile in order to save money. His proposals were
approved, and the first call for tenders for the construction of the
escarps was issued on 12 November 1828.1 The escarp to be
built by contract included the two faces of both the western
demi-basstions and the flank of the southwest demi-bastion. The walls
were duly constructed in the summer and fall of 1829, and Nicolls
pronounced himself satisfied with the work. Late in the fall of the same
year, he called for tenders for another large portion of the
escarp.2 The work this time was on the northern and southern
fronts and was virtually completed by the onset of the winter of
1830-31. Nicolls again issued specifications for another stretch of
wall, and this time, having expressed his complete satisfaction with the
work done by the two contractors during the preceeding summer, allowed
the contracts to be given without tenders to the same
gentlemen.3 In all, the three sets of contracts called for
the construction of 2,120 feet of wall; and, had all gone well, almost
all the escarp walls of the body of the Citadel would have been complete
by the fall of 1831. Things did not, however, go well. On 9 December
1830, 51 feet of the escarp in the southwest demi-bastion
collapsed.4 A few weeks later, another 70 feet of escarp
(this time in the northwest demi-bastion) also collapsed.5
The consequences of these two events were extremely serious; they led to
a questioning of the entire original design, and, ultimately, to many of
the problems which delayed the completion of the Citadel for almost 15
years.
The difficulties encountered in building the escarps did not by
themselves cripple the progress of the work. A second factor was
involved. In September 1831, Nicolls proposed the substitution of a
redan for a curtain and ravelin on the eastern front.6 Even
as he made the suggestion, the last of the escarp on the north, south
and west fronts was being completed. By the fall of 1831, the escarp was
complete to the end of what would have been the east face of the eastern
demi-bastion (in the original plan) which was now the eastern face of
the salients. As long as there was uncertainty about the future of the
eastern front, no more escarp could be built.
Two very different kinds of escarp were built in the summer of 1831.
The last set of contracts was honoured and, for the last time, civilian
masons laboured on the escarp walls. They built the curtain and parts of
the salients (as they were to become). The escarp built in these areas,
though somewhat more substantial than the work which had collapsed, was
still very like it.7 But the escarp design for the rebuilding
of the breach in the northwest demi-bastion was entirely different. The
replacement wall was designed and constructed by the Engineer
department, and was a full three feet thicker at the base than the
original wall had been. In addition, the new wall was buttressed up to
its full height; the old buttresses had stopped at the top of the
batter.
The rebuilding of the failed right face of the northwest demi-bastion
in the summer of 1831 led to a ridiculous situation, wherein part of the
wall was almost immeasurably stronger than the adjacent sections
a fact which made it obvious that some major rebuilding was necessary.
There was, however, neither money nor authority for rebuilding, and the
entire matter waited for the approval of a revised estimate for the
completion of the work. This was not forthcoming until 1838. In the
meantime, only the breach in the northwest demi-bastion was rebuilt.
The provisions of Colonel Jones's revised estimate (1836) finally
settled the issue. The estimate definitely established the shape of the
fort (the proposal for a redan was accepted) and estimated for the
necessary repairs and renewals in the western bastions. The work in the
western bastions was calculated to involve the following:
Right face N. W. Bastion | 62 feet |
Left face N. W. Bastion | 60 feet |
Flank in N. W. Bastion | 434 feet |
Right face S. W. Bastion | 200 feet |
Left face S. W. Bastion | 63 feet |
Flank S. W. Bastion | 35 feet8 |
The estimate also provided for escarps to close up the eastern front.
In all, Jones estimated for the construction or reconstruction of all of
the redan, about 45 feet of the eastern faces of both the eastern
salients at the redan ends, virtually all of the southwest demi-bastion
(except for part of the flank) and about a third of the northwest
demi-bastion. About another third of the northwest demi-bastion had
already been rebuilt. With the execution of the provisions of Colonel
Jones's estimate, therefore, only a comparatively small portion of the
escarp built before 1832 was left standing. This included the whole of
the west curtain, about an eighth of the flank of the southwest
demi-bastion, the south front escarp between the casemates of defence in
the southwest demi-bastion and the salient, the corresponding stretch on
the northern front, and the eastern faces of the eastern salients from
the salient to within about 45 feet of the redan.
Three sorts of escarp wall were proposed in the revised estimate. The
type intended for the rebuilt sections was a modified version of the
escarp used in the rebuilding of the breach in the northwest bastion.
The escarp proposed for the redan was designed especially for a
casemated rampart, and was therefore somewhat thinner than that proposed
for the western bastions, which were to be uncasemated. At the salient
of the redan, there was a short stretch of escarp (220 feet) which had
no casemates behind it. Since this was also the highest escarp wall in
the fortress, it required greater strength than the rest of the redan
escarp and was designed accordingly.
The new escarp walls were completed by 1843. In that year, however,
Colonel Calder decided that the old escarp in the northeast salient was
no longer adequate. "the Climate having . . . so acted on the Masonry as
to render it doubtful whether it will sustain the weight & pressure
of the ramparts."9 Part of the rampart in question had
already been casemated, and Calder proposed to casemate the rest. He
proposed to tear down the old escarp to its foundation (which would, he
thought, be adequate to bear the weight of the new wall) and erect on it
an escarp similar to that in the redan. Like the redan, two escarp
sections were designed a relatively thin one for the casemated
sections and a thicker one for the salient and easternmost part of the
right face of the northwest demi-bastion, which would have to bear the
full weight of the rampart.10
All of the Citadel escarps were completed in their final form by the
end of 1847, and were little modified thereafter. The top of the escarp
and its coping were altered in the casemated portions of the rampart to
assist in the drainage and staunching operations, but this had no
visible effect on the shape of the wall.
The implementation of the provisions of the 1843 estimate left only
small portions of pre-1832 masonry escarp standing, and these were left
alone until the early 1850s. By then, most of the old masonry had begun
to look exceedingly decrepit. Some of the junior engineer officers began
to wonder whether it would not be necessary ultimately to rebuild, but,
in the end, the old walls survived, and the only work undertaken on them
was in repointing them.11
Even as the walls were being repointed, they attracted the attention
of Major General Le Marchant, who, in drawing up the questions put to
the 1856 committee investigating the state of the Citadel, put
particular emphasis on the state of the masonry. There were no fewer
than 20 questions on the subject, ranging from general queries to
specific and pointed enquiries about the type of stone used and the
wording of the contracts under which (as Le Marchant thought,
erroneously) most of the old work had been done. In the end, the
committee delivered itself of the opinion that the walls, though hardly
all that they should be, could, with care, be expected not to fall down
"for many years."12
The Counterscarp
Work on the counterscarp was begun in 1829 and was not completed
until 1848. Unlike some of the other elements in the Citadel the long
delay was not the result of faulty original design. The main reason was
that the counterscarp, being one of the less important features in the
fortress, was allowed to languish while the more essential elements were
completed. Nonetheless, the design changes in the mid-1830s did result
in a radical alteration in the shape of the counterscarp gallery, and
the construction of it and the counterscarp was not without
incident.
The counterscarp, gallery and mines served three separate functions.
The counterscarp covered the escarp from distant cannon fire; the
gallery provided flanking fire for the ditch and access to the mines;
the mines were intended as a defence against sapping operations by a
besieging army. The gallery also provided additional structural strength
for the counterscarp. In the original design of the Citadel, the
counterscarp was provided with a uniform, continuous-arch gallery
running the entire circumference of the fortress. At regular intervals
on all four fronts, countermines branched off the main gallery. At eight
points the gallery widened, at each of the four demi-bastion salients
and at each of the re-entrants on the east and west fronts. The four
stretches of enlarged gallery at the re-entrants were opposite the sally
ports, and it is possible that they were intended as a sort of entrance
hall to the rest of the gallery. Unfortunately, none of the surviving
plans shows any access doors leading to the gallery at any of the
re-entrants, so that there is no way of proving this
hypothesis.13 The four stretches of enlarged gallery at the
salients were the so-called casemates of reverse fire. They were
intended to provide concentrated flanking fire for the ditch, and were
particularly important on the north and south fronts, where there was no
other source of flanking fire.14
By the time of the wall failures and the subsequent crises of the
early 1830s, about two-thirds of the counterscarp and gallery on the
west front and about three-quarters of that on the north front were
either completed or under construction.15 Indeed, when
Colonel Boteler took over, the counterscarp was one of the few parts of
the fortress which he felt he could proceed with without altering the
original design.16 He soon found that he was wrong. The ditch
opposite the left face of the northwest demi-bastion deepened between
the flank and the salient. This, in turn, meant that the loopholes would
be 6 ft. 3 in. above the floor of the ditch at the west ravelin end of
the counterscarp and 9 ft. 3 in. above it at the salient. Colonel
Nicolls's plans were, as usual, ambiguous about his intentions for this
particular stretch of gallery, and Boteler was forced to write London to
request an opinion.17 The correspondence on the subject
dragged on for months also, as usual. At one point. Boteler
dispatched a plan of the gallery as designed by Nicolls, showing the
alternative arrangements.18 At another point, Sir Alexander
Bryce, the Inspector General, sent a plan showing his proposed
alterations in the manner of construction.19 The Inspector
General's plan is interesting, since it provides a clue for the changes
which were ultimately made in the shape of the gallery. General Bryce
feared that those defending the gallery in case of attack would be
vulnerable to grenades thrown by attackers in the ditch, and this,
presumably, was the reason for the suggestion for a segmental or
compartmentalized gallery contained in his plan. The proposal still
envisaged a continuous arch, but it also envisaged dividing the gallery
into sections, each one containing three loopholes. This proposal was
not adopted, but it did provide the germ for the major alterations
proposed for the gallery a few months later.
The casemate of reverse fire opposite the northwest demi-bastion
continued to give trouble throughout the summer of 1832. The engineers
soon discovered that the casemate was being constructed on "made ground"
that is, ground which had been built up with earth from
elsewhere. This meant that the footings had to be sunk to relatively great
depths in order to be secure.20 As the counterscarp neared
the salient, the problem got progressively worse. From a standard 6 ft.
6 in. footing, the depth was increased to 9 ft. 9 in., to 11 ft. 9 in.,
and finally to a full 14 ft.21 This added considerably to the
expense, and seems to have absorbed most of the funds allotted for that
particular stretch of gallery. It is not entirely certain, but it seems
likely that, when the footings were completed work on the counterscarp
and gallery stopped and was not begun again for another six years.
In the meantime, the whole question of the shape of the fort was
being thrashed out. In the winter of 1832-33 no fewer than seven
different estimates for the completion of the Citadel were drawn up. All
seven of them, in one way or another, were based on the assumption that
economies had to be made, and one feature of the fortress which could be
built relatively cheaply was the counterscarp gallery.
The various proposals put forward in the winter of 1832-33 mostly
involved the elimination of elements of the original plan. In one of
Boteler's estimates, a proposal was put forward to build the gallery and
mines as planned on the west and north fronts and omit them entirely on
the other two.22 Boteler was, however, not very happy with
this arrangement, and drew up a second estimate with the intention of
showing the cost of (among other things) the entire gallery and mines as
originally planned.23
Captain Peake's ideas were more radical. He wanted to leave out not
only the gallery and mines, but also the counterscarp itself on the
eastern front.24 This was a little extreme for anyone, and,
in the end, a compromise was reached. In Colonel Jones's estimate, drawn
up in the winter of 1833-34, the gallery was reinstated along the entire
circumference of the fort, and only the countermines intended for the
south and east fronts were deleted.25 This proposal was
accepted.
In the course of sorting out the extent of gallery required, the
whole basic design was altered. The person most responsible for the
changes seems to have been Captain Peake. His design for the gallery
consisted of a series of linked arched cells with both counterscarp and
rear wall of the gallery sharing a common footing.26 The
design was adopted by Jones, who altered it somewhat by redesigning the
dos d'anes and doors; in this modified form, the design was
accepted.27 The reasons for the change are not easy to
determine. One supposes that at least a part of the reason for Peake's
design was its resemblance to General Bryce's suggestion. In addition to
this, the new design was believed to be cheaper to build than the
original.
After the revised version of Jones's estimate was approved in 1838,
work was resumed on the counterscarp and gallery and continued for
another ten years. Most, but not all, of the gallery constructed after
1838 was built to the new design. A few portions were built to the
original specifications. The casemates of reverse fire were abandoned
altogether, and the segmental design was used at the salients, with the
addition of more loopholes.
The troublesome casemate of reverse fire at the northwest
demi-bastion salient may well have been built as a hybrid. The footings,
as we have seen, had been constructed in 1832 before the design for the
gallery was changed. The gallery itself, however, was built to the new
segmental pattern. Since the new pattern was designed with a different
type of footing, one can only conclude that the gallery at the salient
deviated somewhat from the standard plan. Either that, or the
counterscarp has, at that point, the phenomenal footing of 14 ft. by 12
ft.
The Rampart Retaining Wall
The first design for the rampart retaining wall was the work of
Colonel Nicolls, As far as I have been able to determine, none of the
retaining wall was ever built to Nicolls's specifications, but it seems
likely that his design would have been as inadequate for the retaining
wall as the escarp designs were for the escarps. When Boteler and Peake
drew up their revised estimates in 1832-33, the retaining walls they
proposed were substantially thicker than Nicolls's.28
It was Captain Peake who suggested the final design of the retaining
wall for the uncasemated part of the rampart. The retaining wall was
subject to the same stresses as the escarp, and there was some
difficulty in designing a wall which could bear the weight of the
ramparts without being excessively expensive. Peake's solution was to
provide the wall with arched recesses for greater strength. This allowed
the wall to have a thin profile (between 2-1/2 and 3 ft.). The
similarity between the retaining wall designed in this manner and the
segmental pattern counterscarp gallery (also Peake's design) is
striking; indeed, it seems likely that the one suggested the
other.29
Colonel Jones, in drawing up the version of the revised estimate
which was finally accepted, borrowed Peake's design. Virtually all the
documentary material we possess on the subject of the retaining wall is
contained in Jones's estimate. He provided for an arched retaining wall
for the west and south fronts and for parts of the east and north
fronts.30 The remaining sections of the retaining wall were
included in the estimate for casemates. The retaining wall for the
redan, for example, was built as an integral part of the redan
casemates.31
When additional casemating was proposed in 1843, no mention of the
retaining wall was made in the estimate.32 This leads to the
supposition that the existing retaining wall was adapted to meet the
needs of a casemated rampart. At the same time that the additional
casemating was decided upon, it was found necessary to rebuild the
retaining wall in front of some of the casemates at the north and south
ends of the curtain, and the plans and estimates for this service are
the best we possess for the type of retaining wall in use for casemated
ramparts.33
The retaining wall was altered somewhat in the course of the
staunching operations.34 After this, no additional work was
done on them until the committee examining the state of the Citadel
investigated them in 1856, and reported that the walls in the southeast
salient were slightly defective.35 It was not until 1875,
however, that the engineers felt it necessary to make any major repairs.
In that year, a proposal was submitted for the reconstruction of the
retaining wall in the southeast salient. The plan drawn up to accompany
the proposal is the only one available which gives accurate information
about the dimensions of the retaining wall and recesses as they were
actually built.36 The plan also shows something of the
variety of uses to which the recesses were put.
The major provision of the rebuilding scheme was the addition of
buttresses between every second recess. With the acceptance of the
proposal and the construction of the buttresses, the retaining wall
reached its final form.
|