Canadian Historic Sites: Occasional Papers in Archaeology and History No. 17
The Halifax Citadel, 1825-60: A Narrative and Structural History
by John Joseph Greenough
Appendix E: Casemates
The first problem to be overcome in any discussion of the casemates
in the Halifax Citadel is that of determining their number. In fact, one
could make a case for almost any number of casemates, from 54 to 80,
depending on one's definition of the term. "Casemates" may be stretched
to include almost any arched masonry structure; the seven arched rooms
in the cavalier are considered casemates, and the three ravelin
guardhouses are invariably described as "casemated defensible
guardhouses." Even the six storage cellars under the parade square in the
redan have the same basic structure as the casemates. At the other
extreme, a really narrow definition of the term would exclude a number
of the arched structures under the ramparts the privies, for
example, or the shifting rooms. For the purposes of this report, any
arched structure found beneath the ramparts will be treated as a
casemate. This gives a total of 60, counting the three privies, the
shifting rooms, the small casemates in the redan re-entrants, and the
two small arched rooms off the western sally ports.
The second problem arises when one attempts to devise a numbering
system to encompass all 60 casemates. There have been at least three
numbering systems in use since the first was devised in the late 1840s,
and all of them are, in some ways, inadequate. No two of them arrive at
the same total, and all leave some casemates out. The system currently
in use is perhaps the best, but even it has some anomalies. It has, for
instance, a casemate No. 0, completely ignores the casemates of defence
in the western bastions, and for some reason numbers the shifting rooms
as 6A and 15A. Early in my research, it became obvious that a
comprehensive system was necessary, and, at the risk of making an
already complicated situation worse, I devised a numbering system of my
own, which I use throughout this report. It utilizes Nos. 15 through 50
of the previous system and re-numbers the remaining 23. Numbering is
consecutive going clockwise from the southernmost casemate in the
curtain. Even this system has one anomaly: I mistakenly numbered the
privy off the north end of the northern sally port in the curtain and
the small room behind it as 7A and 7B respectively. In fact, as I
discovered later, the two are entirely separate entities, having been
built at different times. However, rather than alter all the numbering
used in the report, I leave the system as it is Following is a
comparison of the standard system with that presently in use.
Nos. 15 (formerly 710 with one unnumbered): South end,
curtain.
Nos. 611 (formerly 114 with two unnumbered): North end,
curtain. The first casemate past the sally port (the privy) and the
small room behind it are numbered 7A and 7B respectively.
Nos. 1213 (formerly unnumbered): The casemates of defence in
the northwest demi-bastion. No. 12 is the westernmost.
No. 14 (formerly 15A): Shifting room, north magazine.
Nos. 1523 (numbered as before): North side, northeast
salient.
Nos. 2433 (numbered as before): East side, northeast
salient.
Nos. 3442 (numbered as before): North side, redan.
Nos. 4350 (numbered as before): South side, redan.
Nos. 513 (formerly 02): East side, southeast salient.
Nos. 545 (formerly 34): South side, southeast
salient.
Nos. 567 (formerly 56): South side, southwest
demi-bastion.
No. 58 (formerly 6A): Shifting room, south magazine.
Nos. 5960 (formerly unnumbered): Casemates of defence,
southwest demi-bastion.
No. 60 is the westernmost.
Building the Casemates
In Colonel Nicolls's original plan for the Citadel, casemates were
intended solely for storage and the defence of the ditch. He provided
for 16 of them, arranged in pairs, to flank the ravelin
ditches.1 The alterations of the early 1830s brought about
two major changes in this plan. In the first place, the decision to
build a redan on the eastern front caused the deletion of four of the
original casemates (those intended for the eastern curtain to flank the
east ravelin) and the addition of eight more casemates of defence to
flank the ditch on both faces of the redan and the eastern faces of the
eastern salients. This brought the total number of defence casemates up
to the present figure of 20.
The second major change resulted from the decision not to build the
north and south cavaliers. Additional barrack space was required, and
Colonel Jones decided that the best solution to the problem would be the
construction of dwelling casemates. The real reason for this change in
policy may have been the result of the escarp collapses of the early
1830s. Casemating was one way of taking the loading weight of the
ramparts off the escarps, and Jones and the Fortifications department
may well have felt that casemating would, in the end, prove cheaper and
more efficient than building escarps of a very thick profile.
In all, Jones estimated for 28 new casemates:2 12
two-storey casemates in the redan for officers' quarters; eight
additional casemates of defence; five storage casemates on the north
front; two small casemated privies on the west front; and one small
two-storey casemate at the redan salient, the bottom storey of which was
also a privy.3
As work proceeded on the casemates provided in the revised estimate,
Jones's successor, Colonel Calder, decided that even 40 casemates would
be insufficient for the needs of the garrison. In January 1843, he
proposed that casemating be extended to fill most of the available space
under the ramparts.4 London responded by inviting him to
justify the additional casemates.5 Calder canvassed the other
department heads to see how much space they would need in the completed
fort, and, on the basis of the information he received, decided that 19
additional casemates were necessary. He formally proposed their
construction in an estimate for the completion of the Citadel dated 22
May 1843.6 He also included in the estimate an item providing
for the rebuilding of the area wall of the casemates of defence in the
northwest bastion to replace an earlier wall which had
collapsed.7
As Calder's estimate was being debated, the redan casemates reached
completion and it became necessary to provide them with their interior
partitions. Unfortunately Jones had neglected to leave a plan of the
proposal for the partitions behind when he left. After a lengthy
exchange with London, a plan was decided upon, and the partitions were
constructed.8
The casemates included in Calder's 1843 estimate included four on the
west front, two on the north front, seven on the east side of the
northeast salient, one in each of the redan re-entrants, two on the
south front and two shifting rooms for the magazines. These were brought
forward in the Ordnance annual estimate in the years following 1843. The
detail provided in these annual estimates was infinitely greater than
the brief sketch of the proposed service provided in the 1843 estimate,
but unfortunately only the text of the Ordnance annual estimate for
1844-45 has been located.9
The new casemates were still in the process of being constructed when
Calder submitted his supplementary estimate in March 1846.10
The casemate provisions of the earlier estimates were reiterated in this
document, but no additional information was provided. The only new
projects involving casemates were the demolition and rebuilding of the
retaining walls of the casemates of defence in the western curtain and
the casemates of defence in the northwest demi-bastion.11
By 1848, all the casemates were completed.12 But the
problems with them were only beginning. Most of them leaked.
Staunching the Casemates
The Engineer department in Halifax spent almost a decade
(1848-56) trying to find a satisfactory solution to the problem of
casemate waterproofing. I have already dwelt at some length on the
problems involved and the solutions adopted. This section is a brief
summary of the earlier chapter on the subject.
The heart of the staunching problem lay in the difficulty of finding
a satisfactory covering for the casemate dos d'anes which would shed
water. The problem was influenced by three main factors. In the first
place, the comparative severity of the Halifax winter, with its sudden
thaws, made frost and water damage in subterranean structures a major
difficulty. This was further complicated in the case of the casemates
by the nature of the drainage system initially adopted to lead the water
off the dos d'anes. In fact the only drainage provided was a lead gutter
in the troughs between the casemates leading to a gargoyle in the
retaining wall and an exposed down pipe. The pipe, needless to say,
blocked up at the first frost, leaving the surface water trapped in the
rampart earth. To cap everything else, neither the casemate arches nor
the dos d'anes were carried very far into the end walls of the
casemates. This meant that there was a comparatively weak join between
the casemate roofs and the end walls, and it was this part of the
casemates which was particularly likely to leak.
Colonel Jones, the engineer responsible for the introduction of
dwelling casemates into the Citadel design, did not anticipate that
leakage would be a serious problem; indeed, he proposed to cover the dos
d'anes with only a layer of tiling laid in cement.13 After
some practical experience with the work, he substituted duchess slates
for tiles,14 and this arrangement remained unaltered until
after his departure from Halifax.
Colonel Calder, on taking over the command, decided that the slate
and cement covering was inadequate for the demands of the climate, and
requested that he be allowed to substitute granite flagging for the
slates.15 London equivocated, but in the end, flagging
replaced both slates and tiles on most of the casemates.
By 1848 Calder had come to the conclusion that flagging alone was not
enough. He was beginning to encounter serious leakage problems, most of
which involved dampness on the end walls of the casemates. To solve
this, he experimented with hipping the dos d'anes and flagging and
counterflagging the hip. In February 1848, he wrote to the Inspector
General of Fortifications to inform him of the extent of the problem,
and of the means he had adopted to combat it.16
The question of waterproofing then became the subject of a
trans-atlantic controversy. London's response was to provide information on
expedients adopted to meet similar situations in other stations (notably
Plymouth and Kingston) and to press for radical alterations involving
the use of asphalt.17 Calder, in the meantime, went on
experimenting with solutions of his own devising, a process which his
successor, Colonel Savage (who arrived in June 1848), continued.
In the course of 1848, Calder and Savage came to realize that
correcting the weak joins at either end of the arches and dos d'anes
would not by itself be sufficient to solve the problem. Something had to
be done about the drainage. The solution decided upon was the provision
of an internal down pipe running from the mid-point of the dos d'ane
gutter through the arch and down inside the casemate beneath. (It is
not clear who was most responsible for the changes probably it
was Savage.) The warmth of the casemate would, they hoped, keep the
pipes from freezing in cold weather.18
In November 1848, Savage had Lieutenant Burmester, RE, inspect the
casemates and produce a report. This document is especially interesting
for the light it throws on the staunching expedients tried up to that
time.19 It reveals that no fewer than five different methods
of casemate covering were then in use. Of the 54 casemates (the
re-entering angle casemates and the privies were not included), 12 had
been flagged and hipped, 30 had been flagged, two still retained their
tile covering, four were covered in a combination of tiles and dry
flagging and six were flagged, hipped and piped.20 In his
report, Burmester did not recommend the introduction of internal piping.
He thought it an unnecessary extravagance. Savage disagreed, but to keep
the expense down, he proposed the re-location of the down pipe from the
centre of the pier wall to the corner formed by the pier and retaining
walls.21
Without waiting for London to react to his proposals, Savage framed
an estimate for staunching the casemates and sent it off in April
1849.22 This was the most elaborate of all the general
estimates ever drawn up in the course of the construction of the
Citadel. It represented a culmination of Savage's (and Calder's)
experimentation with the types of waterproofing needed to withstand
Halifax's formidable climate. It estimated for an extension of the
hipping, flagging and counterflagging to all the casemates (privies and
re-entering angle casemates again excepted), the provision of internal
down pipes, the construction of a system of drains and water tanks, the
alteration of the top of the rampart retaining wall to alleviate some of
the water problems, and a number of lesser changes.23 The
estimate was unique in that it also proposed similar alterations to the
terreplein of the cavalier.
Unfortunately few of the provisions of this very detailed estimate
were ever carried out. The Fortifications department had its own ideas
about the best means of staunching leakage. In the end, a system
involving the extensive use of asphalt and asphalted brick was adopted.
It is unfortunate that we know little about the nature of the change.
The estimates for the service were included in the Ordnance annual
estimates beginning in 1851-52, and, since the texts of these
documents have not been located, we can only speak in very general terms
of the changes made. The major component in the new solution was
"Claridge's Patent Seyssel Asphalte."24 The other materials
were brick, concrete and course shingle. The dos d'anes were altered so
that the hip extended to the centre of the casemate and the down pipe
was moved back to the centre of the pier wall. The top of the retaining
wall and escarp and the chimney casing were also altered, and extensive
use was made of asphalted brick.25 In February 1854, Colonel
Savage reported on the measures adopted26 and was relatively
sanguine about their success.
Ten months later, Savage's successor, Colonel Stotherd, had the
casemates inspected.27 The results were depressing. Despite
all the care and attention lavished on them in the preceding six years,
21 of the rampart casemates and all of the cavalier casemates still
leaked. This revelation provoked something of a minor crisis. It is
impossible to determine the exact nature of Stotherd's response to the
problem, but he seems to have confined himself to repairing the asphalt
and repointing the masonry. This seems to have worked. A second
inspection report, made in the summer of 1856, describes a substantial
improvement.28 And with that, the long history of the
casemate staunching appears to have come to an end.
Subsequent Events
There was a good deal of routine maintenance done, however, and items
for such work appear in almost all of the annual estimates.
Unfortunately few of these documents have survived. In some instances,
we have the abstract of an estimate, but not the detailed calculation of
materials and labour. It is therefore impossible to tell to what extent
the casemates were altered in the course of ordinary repairs.
As an example, in 1862 the Barrack Annual Estimate included the
following Citadel items:
Citadel. Sheet the ceiling of all the rooms £70
Citadel. Cavalier Casemates. Renew the floor boarding
£1,466
Citadel. No 18 Casemate [standard system No. 25]
Convert into a Woman's Wash House £111
Citadel. Ablution Room No 23 Casemate. [Standard
system No. 30]. Provide 5 baths £64
Citadel. Provide 1 Steel Oven and 15 Boilers £249
Officers' Quarters, External Pointing. £11
Officers' Quarters. Preparatory Repairs. £9
Soldiers' Quarters. External pointing £94
Soldiers' Quarters. Preparatory Repairs £28
Soldiers' Quarters. Internal Whitewashing
£22229
It would be interesting to know if, for example, the cavalier floor
was much altered in the process of being renewed, but the lack of detail
in the abstract makes it nearly impossible to find out. We can,
therefore, only conclude that the casemates were subject to continual
repair and renewal work and may have been substantially altered from
their original form.
We do possess detailed estimates for three such alterations. In 1856,
a supplementary estimate for the construction of cess pits and drains
and the alteration of the soldiers' privies was submitted and
approved.30 This is especially important, since we have no
other documentation for the privies.
The other two alterations for which we possess estimates both reflect
the continuing preoccupation with waterproofing. In 1859 an item was
inserted in the Fortifications annual estimate for 1860-61 for the
construction of a subterranean area between the pier of the southernmost
casemate in the curtain and the adjoining ramp.31 In 1861 two
items were inserted in the Civil Buildings Estimate for 1862-63 for
waterproofing and ventilating the magazine shifting rooms and for
renewing the floor of the south magazine shifting room.32 It
is not certain whether either of these proposals was carried out. They
probably were.
|