Canadian Historic Sites: Occasional Papers in Archaeology and History No. 17
The Halifax Citadel, 1825-60: A Narrative and Structural History
by John Joseph Greenough
". . . and keep your powder dry!"
From Ballads of Ireland, Col. Oliver's
Advice, Valentine Blacker
I
The attempts to staunch the casemates absorbed most of the energies
of the engineering staff at Halifax during the last decade of the
Citadel's construction. The problem involved was fundamentally the
result of four different but related factors. The first was the
necessity of completing the casemates in such a way as to allow them to
perform their allotted functions effectively. This was vastly
complicated by the second factor: pressure from the military authorities
to use them as barracks. The third factor, in some ways the most
frustrating, was the age of the work. A good many of the casemates had
been standing empty for years before the construction finally reached a
stage where they could be put to use, with the natural result that the
process of staunching involved both building and repairing
simultaneously. The fourth factor was the inadequacy of the original
design. This was less because of incompetence on the part of Colonels
Jones and Calder; the casemates were of comparable quality to those
built elsewhere. But no one knew precisely what features could be used
effectively in a permanent fortification in the damp Halifax
climate.
These same four factors underlay the difficulties experienced with
other parts of the work carried on at the same time as the staunching.
The problem of waterproofing, moreover, ultimately affected almost all
the other parts of the fortress. While the casemates remained
unfinished, the ramparts, armement and parade ground could not be
completed: the magazines could not be used except as storage depots for
other works in the Halifax area, and the glacis could not be built.
There was simply not enough labour to do all the work at once. This
inevitably exacerbated the age factor, since the longer the remainder of
the work was postponed, the more decrepit the existing buildings became.
In the end the engineers found themselves caught in a kind of
nightmarish race to get the fortress finished before its aging fabric
went irretrievably rotten.
The last decade of construction was, therefore, characterized by
interconnected routine work, with the dominant theme of casemate
staunching played out against a counterpoint of increasing urgency. The
period can be divided into three phases. In the first, lasting until
about 1850, the momentum of building continued, all the while being
gradually slowed and interrupted by the growing demands of the
waterproofing problem. At this time the final provisions of the revised
estimate were carried out and the last attempt was made to introduce new
features into the original plan. By the end of this stage, it was
obvious that the primary concern was not improving the work but
preserving what had already been built. In the second phase, lasting
from 1850 to about 1854, the waterproofing brought almost all other work
to a complete standstill, while the decay of the older portions of the
masonry was accelerated. In the third phase, from 1854 to 1856, all the
problems, delays and faulty judgements of the previous quarter-century
finally came home to roost, and the project came closer to foundering
completely than it had at any point since the early 1830s.
The most characteristic activities of the first phase were the
removal of earlier failed work and the abortive attempt to introduce
prison casemates; of the second, the attempt to install the armament.
The third phase was characterized by an almost frantic attempt to renew,
restore on rebuild parts of almost all the major components of the
fortress, including the cavalier and magazines. Even the casemates.
after almost 10 years of continuous labour on the problem of
waterproofing, remained a major source of worry and complaint. In the
end, disaster was averted, but it had been (to use a Wellingtonian
phrase) "a near run thing."
25 "Plan to accompany the Report on the Demolition of the old Magazine,"
1847.
(Public Archives of Canada.)
|
II
By the mid-1840s, one of the few remaining routine tasks which did
not involve the casemates was correcting earlier mistakes and
removing those features of the early design no longer felt to be
necessary. The first casualty was the old (1812) magazine, which had
been standing empty for 19 years and obviously impeded the completion of
the parade square. In the spring of 1847, Calder got permission to
remove it. As it was an almost embarrassingly solid piece of work, the
Fortifications department did not want to spend the time and effort
necessary to demolish it by conventional means. The only alternative was
to blow it up, and even this took considerable time. Between 24 March
and 6 April, working parties laboured with crowbars, picks and sledge
hammers on the business of constructing galleries in the masonry walls
for the gun powder charges. In all, 22 chambers were cut into the walls
and were packed with charges of between 9 and 16 pounds of gunpowder
each.
On 7 April, everything was ready. The officer in change of the
demolition described the results.
The charges being fired, the foundations were blown away, the
walls rose about 3 feet, and falling with a low rumbling sound, crumbled
to pieces, hardly two stones being left together. Not a stone was blown
50 yards from the building.
The arch, of course, fell in; all the charges exploded except the
four in the North Angle which was consequently left standing . . .
.
The demolition was most complete, and the magazine now presents
the appearance of a shapeless mass of ruins.1
Colonel Calder pronounced himself pleased with the operation. Indeed,
he was so impressed with the speed and efficiency of the demolition that
he proposed similar measures for one of the other failures earmarked for
removal.
I beg to propose the removal of the West Ravelin (which is to be
taken down and rebuilt) by a similar process, but for this I consider it
necessary to obtain your [Burgoyne's] sanction, as to effect it
about 20 barrels of gunpowder will be required, an expense which will be
amply covered by the diminution of labour.2
Calder waited almost a year for a reply to this proposal. When it
finally became important to get the matter settled so that he could
proceed with the rebuilding of the ravelin, he dispatched an informal
query to London. "Col. Calder presents his compliments to the Inspector
General of Fortifications and begs to acquaint him that the last
paragraph of his letter No 193 . . . has not been replied
to."3 The fact was that London had lost the original letter:
one of the clerks had to annotate the margin of Calder's query, "I
cannot put my hands upon the origl letter No
193."4 When it was finally found, the Inspector General
responded by asking Calder why he wanted to proceed with the scheme.
Calder restated his reasons.5 After another delay, Burgoyne
decided to forbid the use of explosives in the demolition on the grounds
that it might be possible to re-use some of the stone from the west
ravelin in rebuilding.6
This ended the brief vogue for dramatic demolition of old mistakes.
In fact, apart from the two cases mentioned above, a surprisingly small
amount of the supposedly defective work of the early period was ever
altered. Most of the work in question was, of course, in the escarp
walls, and some of the basic rebuilding and repairs there had already
been done by Nicolls and Boteler in 1831-32. Colonel Jones
estimated in 1834-36 that only 574 feet of the remaining old walls
would have to be rebuilt.7 This was only a portion of the
original escarp and it was demolished by means less dramatic than
explosives. In the end the engineers made do with the remaining old
walls, partly because the masonry in question, though shoddily built,
showed a complete disinclination to collapse. After the demolition of
the west ravelin in 1848-50, the whole question of the old work was
shunted aside and partly forgotten. It was not until 1855 and under
rather different circumstances that it became again an issue.
III
As the last of the old work was being removed, Colonel Calder made
the last attempt to introduce a new feature into the overall design of
the Citadel. This was in response to a peculiar and specific sort of
accommodation problem. The first soldiers to have the honour of
inhabiting the Halifax Citadel had been the military convicts. As early
as 1845, a strongroom and guardhouse had been fitted up for prisoners
in two of the defence casemates (Nos. 54 and 55).8 This was
apparently only a temporary arrangement to serve until cells designed
for the purpose could be built. Such cells were included in the 1843
estimate for alterations and renewals and were to be located above the
end casemates of the cavalier.9 But even after the cells were
built there was still not enough room for the convicts. On 7 August
1847, Calder submitted a proposal for 12 more cells to be placed under
the ramparts on the south side of the southeast salient.10
His design called for a complicated arrangement of two-storey arched
compartments connected by a corridor at the rear. He estimated the total
cost of the scheme at £2,410 19s. 7-1/2d.11
London not only approved the scheme but, in a rare burst of
generosity, actually enlarged upon it. Calder shortly received a revised
design which included two additional compartments for first-class
prisoners and a more complicated system of heating and ventilation. The
only objection which the Ordnance raised was to the proposed location of
the new work. The south face of the southeast salient was considered
inappropriate because of the lack of space available for the enlarged
scheme, so it was suggested that the work should be put on the east side
of the salient.12
26 The west ravelin rearmament, ca. 1875. The rearmament of the ravelin
consisted of cutting an embrasure at the salient and removing one
embrasure from each face.
|
Calder, doubtless amazed at this unexpected development, could only
concur. He incorporated all the changes and re-submitted the design
on 15 November.13 Even as he was doing so, however, London
was having second thoughts about the whole project. The problem of
accommodating prisoners was essentially an army matter, and the Ordnance
had seen fit to submit the scheme to the Secretary at War for an
opinion. The secretary, Mr. Fox Maule, disliked the idea and decided
that it would be better policy to build a gaol large enough to hold all
the garrison convicts somewhere outside the Citadel.14 The
Board of Ordnance accepted the recommendation and instructed Burgoyne to
inform Calder.15 In the end, the cells over the cavalier
cookhouse remained the only military prison within the fortress.
IV
It was not until 1846 that the Ordnance staff in Halifax addressed
themselves to the task of composing an armament proposal for the
Citadel. In that year, Lieutenant Colonels Calder and Jackson (the CRA)
drew up a scheme which entailed 94 pieces of ordnance, including five
8-inch guns, thirty-one long 32-pounders, eighteen short 32-pounders,
twenty 24-pounders, twelve mortars and eight howitzers (see Table
4).16 On 15 September 1846 the Director General of Artillery
approved the plan and initiated the process of
installation.17 Almost ten years elapsed before the bulk of
the armament was installed.
|
Table 4. Proposed Armament, 1846* |
|
Location | Guns
|
Mortars
| Howitzers
|
|
| 8 -in., 9'0" | 32-pr., 9'6" |
32-pr., 6'6" | 24-pr., 6'0" |
13-in. | 8-in. |
8-in. |
|
South front |
| 3 |
|
|
| 4 |
|
|
West front |
| 6 | 2 |
|
2 |
| 4 |
|
North front |
| 4 |
|
|
| 4 |
|
|
East front |
| 8 |
|
|
| 2 | 4 |
|
Salients, all fronts | 5† |
|
|
|
|
|
|
|
North ravelin |
|
| 6 |
|
|
|
|
|
South ravelin |
|
| 6 |
|
|
|
|
|
West ravelin |
|
| 4 |
|
|
|
|
|
Salients, all ravelins |
| 3† |
|
|
|
|
|
|
Cavalier |
| 7 |
|
|
|
|
|
|
Casemates |
|
|
| 20 |
|
|
|
|
Total | 5 | 31 | 18 |
20 | 2 | 10 |
8 |
|
*Adapted from a return in PAC, MG12, WO55, Vol. 880, p. 913.
†One in each salient.
The first stage of the process involved the manufacture of carriages
for the guns, the acquisition of the guns themselves, and the
construction of the stone platforms on which the greater part of them
would be mounted. The first matter was the responsibility of the Royal
Carriage Department; the second, of the Board of Ordnance, and the
third, of the Engineer department in Halifax. Since a coordinated
interdepartmental effort was involved, delay and complications were
inevitable, and it was well over two years before all the orders were
filled.
The most serious misunderstanding arose over the order for 24 siege
gun platforms after Lieutenant Colonel Alderson's pattern. These were
intended for mounting the mortars, howitzers and four of the
32-pounders.18 The Ordnance staff in Halifax included them in
the order for traversing platforms and carriages sent in to the Carriage
department in the spring of 1847.19 Two years later the
Carriage department decided that the platforms might not be their
responsibility. The gentleman in charge. Mr. Gordon, wrote to General
Burgoyne,
I feel assured you will excuse my addressing you point blank (as
the saying is) upon the enclosed order for Halifax.
I made inquiry from the Assistant Director General of Artillery
thereon, and he gives me the dates and authorities only, but I want
measurements or working plans and I am sensible you will afford me such
as to enable me to carry out this outstanding order.20
After some discussion, the Board of Ordnance decided that the
Carriage department ought to be relieved of the task of making the
platforms, and instructed Burgoyne to ask the Commanding Royal Engineer
in Halifax why they had not been included in the Engineer Demand of
Stores in the first place.21
By the time this finally got back to Halifax, Colonel Savage had
replaced Calder as Commanding Royal Engineer. Savage had no idea why his
predecessor had requested the platforms from the Carriage department,
and could only promise to include them in the Ordnance annual estimate
as required.22 By then it was obvious that the armament could
not be mounted at all until the problems of waterproofing the casemates
were solved, and the whole question of equipment was temporarily
sidetracked. Fortunately, the Artillery was in no hurry to mount the
guns and, except for the occasional enquiry on technical matters,
nothing more was heard about armament for two years.
By the spring of 1851, however, the Director General of Artillery was
beginning to get impatient. The CRA was requested to report on "the
condition of the fort with respect to its state of preparation for
mounting the Ordnance."23 The CRA relayed the request to
Colonel Savage,24 who answered that the Citadel would not be
in any state to receive armament until the summer of 1853. Even this
date proved optimistic. When the question was put to him again in
January 1853,25 Savage was able to approve the mounting of
only part of the armament for the following summer.
[The] following description & number of Guns may be mounted
viz:
5-8 inch 9' 0" long at Salient angles.
10-32pr 9 . . 6" on Cavalier & Ravelin
20-24d° 6 . . 0 " In Casemates
16-32d° 6 . . 6" Ravelins.26
The remainder could not, he thought be mounted until the following
year.
The Ordnance did its best to prevent Savage from carrying out his
plans for 1854. The mounting of armament on the rest of the work
depended on the completion of the staunching project and the
construction of the ramparts and terreplein. While the former appeared
to be going ahead successfully, London prevented the latter by refusing
to allow Savage the sum provided for the service in the annual estimate
for 1853-54. Three months after he had given his optimistic prediction
to the CRA, Savage wrote to the Inspector General proposing that the
funds allotted for completing the glacis be used instead for the
terreplein and parade.27 London replied with surprising
speed, granting permission to make the substitution.28 Since
the work was not included in the annual estimate for the following
year,29 it would seem that the ramparts were constructed in
the summer of 1853, and, in all likelihood, most of the rest of the
armament was mounted the following summer.
Whether it would stay mounted was another matter. By the fall of
1854, serious questions were being raised about the future of the
cavalier, and after a brief period of optimism, it was becoming
depressingly evident that the casemates were still displaying a
pronounced tendency to leak.
V
The first indication that parts of the Citadel were falling to pieces
came on 19 October 1852, when the Ordnance Storekeeper, Mr. Ince,
discovered that the door of the north magazine would not open "in
consequence of something having fallen against it."30 On
examination, Colonel Savage discovered (probably to his horror) that
"the floor, which was previously in a decayed state, had suddenly given
way, from the weight of the powder and the decay of the
joists."31 Savage had already provided for repairing the
floor in the annual estimate for the following year, but the sudden
collapse took him by surprise, and he could no longer wait for the
estimate to be authorized. He therefore requested that the Respective
Officers formally propose a special estimate. The Respective Officers
replied three days later:
We have to request you will immediately take the necessary steps
to bring the subject under the notice of the Inspector General of
Fortifications with a view to obtain as soon as possible the Master
General and Board's authority for the repair of the floor for the
preservation of the powder.32
The next day, Savage formally requested permission to make immediate
repairs, stating that the expense could be defrayed from the savings on
various items of the annual estimate for the preceding
year.33 London was quick to authorize the expenditure, and
the repairs were carried out in the course of the
winter.34
In spite of his experience with the north magazine, Savage was
somewhat startled when, a few months later, he examined the floor of the
south magazine while alterations to the powder bays were being made:
I was led from the appearance of a depression in the surface of
the floor, to examine its state beneath . . . it was found that the
joists, plates and boarding throughout were in the last stage of decay,
evidently from the same cause that rendered necessary the renewal of the
floor of the north Magazine, and which makes it absolutely
necessary to renew this floor before the bays can be arranged or the
powder again stored therein.35
This discovery made it necessary to formulate yet another special
estimate, but this time Savage decided to use a new method of repairing
the floor. Acting on a suggestion from the Surveyor of the Ordnance, he
proposed to use
fine Seyssel Asphalte without grit in lieu of the joists and
planking, which substitution I consider may be effected as an
experiment, as it is probable that asphalte in this situation, not being
exposed to the direct action of the weather it [sic] may be found
to answer to the desired end.36
He enclosed a special estimate and a demand for stores amounting to
£158 5s. 0d.
Despite the fact that Savage's suggestion was made at the height of
the asphalt mania, London decided that it would not be appropriate to
use the material on the magazine floor. General Burgoyne recommended
that the floor be repaired in the same way as the one in the north
magazine (apparently with a new wooden floor) and the board approved his
recommendation.37
The two magazine floors were repaired and the buildings restored to
normal use by the summer of 1853. There followed a brief respite. It was
to be a year and a half before the next serious problem arose.
VI
By the fall of 1853, Colonel Savage thought that the end of the
Citadel construction was in sight. The Ordnance annual estimate for the
following year reflected this belief. There were only two items in it
for the Citadel.38 One, amounting to £2,681 12s. 3d.,
was for the completion of the glacis and parade square, and this was
believed to be the last major expenditure on the work. The Assistant
Inspector General wrote, in forwarding the estimate to the board, "With
the sum here proposed the Coming Rl Engineer
expects to complete the Citadel in 1854-5."39
The second Citadel item for £1,256 2s. 11d. was for the renewal
of the cavalier colonnade and was considered absolutely necessary for
the occupation of the building by troops. This was an ominously large
sum to be spent on repairs, but it could easily be explained. After all,
the cavalier was almost 25 years old and repairs were a matter of
routine in a building that age. At this point, no one seriously
considered more drastic measures to be necessary.
This mood of optimism lasted for some time. In February, Lieutenant
Parsons drew up his memorandum on the effectiveness of asphalt in the
Citadel; while he admitted that it had not worked in the case of the
cavalier, he did not speculate on the reasons.40 In
forwarding Parsons' report to London, Savage noted that
the very imperfect state of the Escarp and Retaining walls of the
Cavalier erected many years since, render any attempts to secure it
against leakage short of rebuilding the upper part of it, a measure of
considerable difficulty, if not an impossibility.41
Apart from this observation, which Savage appended almost as an
afterthought to a long report, the whole question of the cavalier's
suitability received little attention either in Halifax or in
London.
When Lieutenant Colonel Richard Stotherd inherited Savage's command
in June 1854, it seemed that he would have the good luck to be the first
Commanding Royal Engineer in more than a quarter-century to avoid
trouble with the Citadel. His first summer, in fact, passed quietly
enough. The only matter concerning the Citadel which needed particular
attention involved a special estimate (amounting to £22 12s. 10d.)
which provided for altering the position of the stoves in the cavalier
to keep the casemates warm in winter.42 This was approved by
London in just over a month.43 Stotherd's first annual
estimate, dispatched on 25 September, asked for only £1,902 for
the Citadel, most of it for completing the glacis. Only £100 was
for staunching the casemates and there were no items at all for
repairing the cavalier.44
But during the winter of 1854-55, two events occurred which shattered
the satisfaction of the Ordnance staff in Halifax, at least in regard to
the Citadel, and Colonel Stotherd found himself faced with the worst
crisis in the fortress's history since Colonel Nicolls's walls collapsed
in 1830.
The first event was a systematic examination of the casemates in
November 1854. This revealed that, despite all the measures undertaken
in the preceding eight years, 21 of the casemates were to some degree
damp. The extent of the problem varied from casemate to casemate. Some
were only slightly wet: others were uninhabitable. The rampart
casemates, however, were in relatively good condition compared to those
in the cavalier. Except for the small end casemates and the rooms over
them, the entire building was completely uninhabitable.
A very considerable extent of dampness is observable in the upper
rooms and which penetrates for the most part to the lower floor . . . .
The dampness arises chiefly from the very defective masonry of the
escarp and retaining walls which admit the wet through the joints so as
to penetrate beneath the asphalte. Owing to the frost of last winter,
there is reason to believe that the Asphalte is considerably injured
beneath the earth of the Terreplein.45
Stotherd reported all this to London in a rather gloomy letter. He
was particularly dissatisfied with the cavalier.
It is now evident that a very considerable expense will have to be
incurred to make the building water tight and habitable, apparently
owing to the defective nature of the masonry in the external walls . . .
. such is the state of the walls that it is considered doubtful whether
the firing of the heavy ordnance mounted thereon would not shake the
walls considerably or possibly bring them down.46
As for the ramparts casemates,
I regret to inform you [Burgoyne], notwithstanding the
hopes entertained by my Predecessor that the approved application of
Seyssel Asphalte would be successful in securing them against leakage,
that some of them have recently become damp from the percolation of
water through the Arches: whether this arises from Cracks caused
by the frost during the previous winter, or from fractures in the
coating arising from the pressure of the overlaying shingle and earth,
aided by the heavy traffic in getting up and mounting the platforms and
guns, it is impossible to determine without opening the ground which at
this season cannot be effected owing to the frost.47
He estimated that complete repairs would cost around £6,000,
most of which would be needed to repair the cavalier, where he proposed
to rebuild the entire top of the building from the springing of the
arches up. He was less explicit about dealing with the leakage in the
rampart casemates, but apparently he contemplated a continuation of the
existing system of staunching.
Two weeks later, Stotherd dispatched a second letter requesting an
immediate delivery of asphalt so that work on the casemates and cavalier
could begin as soon as practicable in the spring.48 The
response was surprising. After nearly 10 years of experimenting with
asphalt in the Citadel, the Fortifications department was beginning to
wonder whether it was, in fact, entirely suitable for waterproofing in
the Halifax climate. The Assistant Inspector General, Colonel George
Judd Handing, wrote back, enquiring whether "flat tiles laid in cement"
would not be more suitable.49 One wonders whether Harding
was aware that his suggestion had been tried before, with indifferent
results, by Colonel Jones more than 10 years earlier.
27 A modern impression of the appearance of the cavalier prior to the
installation of the permanent roof in the summer of 1855.
|
Before Stotherd even got Harding's suggestion, the second, disastrous
event occurred. On 8 February 1855 Halifax experienced one of its very
rare earthquakes, and among the most vulnerable buildings in the entire
city was the aged, decrepit and top-heavy cavalier. The report on the
damage, submitted by the Clerk of the Works and two of the junior
engineer officers, Captains Philip Barry and Henry Grain, was possibly
the most pessimistic summary even produced in the entire course of the
Citadel's construction.
We are of opinion from the vast quantities of water discharged
through the arches and walls [of the cavalier] during the heavy
rains of the past week, that the shock must have, to some extent,
contributed to the further disturbance of the masonry so as to increase
the leakage . . . .
The external walls appear, to a very considerable extent, to be
splitting or separating longitudinally through the centre from top to
bottom, owing to the expansive action of the frost on the moisture in
the masonry, and which under present circumstances there is no
possibility of preventing, nor does it appear to us, that there is any
mode of repairing, at a future period, those defects, short of taking
down and rebuilding the whole of the external walls, as no pinning or
pointing would avail to render them secure in the event of a recurrence
of Earthquake, much less to bear the concussion from discharging the
guns at present placed on top.50
They concluded by recommending that no attempt be made to staunch the
arches while the walls were "in a condition apparently so irremidiable
[sic]."
A second report, appended by Captains Barry and Grain, was if
possible even more outspoken than the first:
We . . . would beg to suggest, that in a Military point of view it
may be well to take into consideration the value of the Cavalier as a
work of defence. To us it appears not to be well calculated for
its object in that particular, its greatest advantage ls that of
affording quarters for troops, and therefore, and as the escarp of the
curtain of the West front is fast approaching a state of delapidation,
which must in a few years make its reconstruction absolutely necessary,
it may be worth while to consider the propriety of constructing
casemates under the ramparts to afford the requisite
accommodation.51
The two officers then went on to suggest that the cavalier be
demolished to make way for "a tower . . . to mount three or four heavy
guns" which would both fulfill all the military functions of the
cavalier and allow more space in the fort's interior.
28 "Plan and Section of the top of the Cavalier showing [sic] the
proposed Arrangement of Seven Guns also the Flagging and Counterflagging
of Arches over the Existing Tiles," 1846. The flagging and
counterflagging detailed in this plan wer ultimately superseded other
materials (most notably asphalt), but the curbs, pivots and racers were
installed as shown here.
(Public Archives of Canada.)
|
This second report was not only outspoken, it was downright
dangerous. In a mere half-page, two junior officers had managed to
question the wisdom of the original designers of the Citadel, revive an
idea which had been forgotten for nearly 30 years, and, worst of all,
raise the whole question of the old remaining contract masonry which had
been often condemned but never replaced. One can imagine Stotherd's
reaction when he read it. It was beginning to look as if the major work
in his command was about to disintegrate.
In forwarding the reports on the earthquake damage to London,
Stotherd adopted a cautious, almost contradictory stand on the
suggestions contained in them. He began by confessing that, since it was
his first winter in Nova Scotia, he was far from being an expert on the
effects of the local climate. He then went on to state that, in its
present condition, he could not recommend the staunching of the upper
parts of the cavalier. But he was uncertain about the best course to
adopt.
The proposition of Captains Barry and Grain . . . to form
Casemates under the Curtain of the west front, with a tower in the
centre, in lieu of the Cavalier is worthy of consideration, for the
reasons they adduce, and I shall await your instructions to have it
regularly brought forward with Plans &c
On the other hand, he noted that the cavalier had once been
a very useful building, and I am strongly of the opinion that it
should revert to that state and be made available for shelter for
troops, and for stores, by covering it with a wooden roof similar to
that which I understand existed prior to the attempt to secure the
arches from leakage.52
Such a roof would, he estimated, cost around £600.
The Ordnance was not disposed to accept any radical suggestions. In
fact, the whole apparatus of the Ordnance department was under
tremendous strain because of the Crimean Wan, and the department was to
undergo a major revolution in the near future. The officials in London,
uncertain about their own futures, were not about to make major
decisions. Their only response to Stotherd's letter and the gloomy
reports it enclosed was a brief note asking whether it was necessary to
restore or replace the building at all. No mention was made of the
possibility of tearing the cavalier down, and Stotherd was requested to
report on the "extent of the repairs required" so provision could be
made for them in the annual estimate for the following
year.53
This was virtually the last instance of the Board of Ordnance
handing down a decision on matters relating to the Citadel.
Appropriately enough the board ended its superintendance of the work on
a note of administrative equivocation. Stotherd was enjoined to await
events. He did not have to wait long; events were quick to catch up with
him. He was soon facing both a political challenge from forces which had
never before had any effective control over Ordnance works, and the
pressures of providing necessary services within the Citadel. The first
of these, which was to be the most difficult to manage, will be
discussed later. The second was to shape the concluding stages of the
construction of the work.
29 The interior of the redan casemates, ca. 1890.
(Public Archives of Nova Scotia.)
|
30 Interior of one of the redan casemates, ca. 1890.
(Public Archives of Nova Scotia.)
|
VII
London was wrong in assuming that the cavalier was of little
importance to the Halifax garrison. It was true that the station was
well below strength in the winter of 1854-55 because most of the British
army was in the Crimea. Even the small remaining garrison, however,
needed more barrack space. On 21 June Stotherd submitted an estimate
amounting to £944 0s. 7d. for the restoration of the
cavalier.54
The scheme put forward in the estimate was essentially an elaboration
of the roofing proposal which Stotherd had made at the end of his
February letter. Besides installing a timber roof, it proposed to alter
and enlarge the chimneys, to point the defective masonry joints and to
whitewash the rooms. This implied the abandonment of the cavalier as a
defensive work. Although the guns were left in place, the enlargement of
the chimneys and the installation of the roof would make it difficult to
get the gun positions cleaned for action in time of war and impossible
to fire them in peacetime.55
Authority to proceed with the scheme was quickly
forthcoming.56 By August Stotherd was able to report that he
expected to be finished with the work within two months.57 By
this time, Stotherd had found solutions to most of the remaining
problems of the Citadel. He no longer thought in terms of major
alterations, but only of minor repairs which, he hoped, would be
sufficient to silence criticism of the work and to keep it in a
tolerably good state of repair. It is difficult to escape the conclusion
that most of the items proposed were at least partly cosmetic in nature,
but they did at least manage to keep everyone satisfied. In this rather
undignified way, the Citadel project limped into its ultimate stage.
The nature of Stotherd's work is demonstrated by the type of item he
inserted in the annual estimate for 1856-57. Of the £2,900
estimated for the Citadel, over two-thirds (£1,795) was for minor
repairs of one sort or another, including £959 for repairing the
asphalt over the arches, £38 for pointing the arches in the redan,
and £529 for pointing masonry in the escarps, counterscarps and
magazines.58 This list covers two of the three major sources
of complaint (the old escarps and the waterproofing) in the cheapest
way possible.
In a report on the defence of the Nova Scotia command, submitted at
the same time as the annual estimate, Stotherd defended his policy,
especially in regard to the pointing.
[The] Curtain has been too long left in a most disreputable state
and the comparatively trifling sum [£528 17s. 10d.]
required for the extensive and very necessary repairs to the Scarps
and Counterscarps of two long neglected fronts together with the
pointing of the two magazines and their enclosures will, in my opinion,
be most profitably expended.59
The effectiveness of Stotherd's measures was varied. His assessment
of the strength of the old walls was borne out by subsequent experience
with them (see "The Very Model of a Modern Major General"). The
experiment with the roof of the cavalier proved equally successful. A
tabular statement of the condition and usage of the casemates drawn up
in June 1856 reported that there was only a slight appearance of damp on
the west wall and this could be easily corrected by additional pointing
of the masonry.60 The same statement revealed, however, that
Stotherd had been less successful with the other casemates. A surprising
number of them still leaked or showed evidence of damp on one or another
of their internal walls. The report treated each case individually;
there was no longer any attempt to assign blanket causes for the
problem. One was damp because of faulty drainage; another because of
decaying masonry; a third because the terreplein had not had time to
settle properly and so on, down a whole list of similar minor
faults. In other words, the problem had reached the stage where it could
be treated as a minor housekeeping difficulty, and no further large sums
of money were needed to correct it.
As for the other features of the fort, most required only minor
alterations. Most of the armament had been installed.61 After
a bad start, marred by the complete undrinkability of the water, the
water tanks were in the course of being repaired.62 It was
not a particularly heroic ending but, with the exception of the glacis,
the Citadel was virtually finished.
|