|
|
Canadian Historic Sites: Occasional Papers in Archaeology and History No. 8
The Canals of Canada
by John P. Heisler
Problems in the Construction of Canals: Land and Contracts
I
i
One of the most tedious and troublesome aspects of canal
construction was the acquiring of land through which to build the
waterway. In the case of the Rideau, getting land proved to be the most
time-consuming and unrewarding of the duties which devolved on Colonel
By. From the very beginning he realized that it would be a major and
ticklish problem and he wrote to the lieutenant governor, Sir Peregrine
Maitland, about it on 2 January 1827.1 Maitland had already received
communications from the British government and from the
governor-in-chief, Lord Dalhousie, requesting him to afford By every aid
and assistance within his power in procuring the required
land.2 In his letter to Maitland, By expressed the belief
that judging from the difficulty he had encountered in obtaining
information relative to the proprietors of the land through which he
proposed to cut the canal, the work could not progress as rapidly as the
British government desired without some regulative Act authorizing him
to take possession of any amount of land which he might require. By
believed that "a Bill to that effect will meet with less opposition
before the line of Canal is correctly ascertained, than when each
individual can judge of the advantages or disadvantages he, or his
neighbours, may sustain from the proposed Canal."3 Maitland
apparently acted quickly. On 17 February 1827, the legislature of Upper
Canada passed the Rideau Canal Act.4
Although the canal was for the British government, the Act gave to
Colonel By, as a representative of the King, "all the powers which the
Upper Canada government would have possessed had it undertaken the
work."5 The first section of the Act stipulated that the
officer employed by His Majesty to superintend
the work was authorized to set out and ascertain such parts of the
country through which the canal was to pass, as he shall think necessary
and proper for making the said Canal, Locks, Aqueducts, Tunnels and all
such other improvements, matters and conveniences as he shall think
proper and necessary for making, effecting and preserving, improving,
completing and using in the said navigation."6 The third
section of the Act declared that "such parts and portions of land or
lands covered with water, as may be so ascertained and set out, by the
Officer employed by His Majesty, as necessary to be occupied for the
purposes of the said Canal, and also such parts and portions as may upon
any alteration or deviation from the line originally laid out for the
said Canal, be ascertained and set out as necessary for the purposes
thereof shall be forever thereafter vested in His
Majesty."7
By could therefore demand any land he required for the Rideau Canal.
The provincial statute stipulated, however, that the arbitrators for
fixing the value of the lots taken could not be appointed till the canal
was completed. Accordingly, some proprietors were reluctant to dispose
of their land though it was perfectly clear that there would be no
difficulty in adjusting eventually the claims of the proprietors, if By
could show that the land he had taken was required for carrying on the
work.8 At the same time, By could make an immediate purchase
of the land required for the canal provided this could be done on
reasonable terms.9 Previous to closing any such bargain,
however, he was required to make a special report accompanied by a
regular survey for His Majesty's consideration. For example, on 31 March
1829,10 the military secretary informed the commanding Royal
Engineer in Canada that after perusing the documents relating to the
purchase of certain lots of land in the vicinity of the Hog's Back on
the Rideau River belonging to R. D. Fraser and Dr. Munro, His Excellency
approved of the purchase made by Colonel By of the front of Fraser's two
lots containing about 45 acres for the sum of £400 sterling. Later
in September,11 a similar communication between the same two
officers contained His Excellency's approval to purchase Dr. Munro's
land comprising 900 acres for £1,000 sterling and the remainder of
Fraser's land comprising 455 acres for £380 sterling. Since the
Hog's Back was a leading feature of the canal, the government needed
land there on which to construct defence works at a future time and to
settle on it a loyal population interested in protecting the dam and
canal. By recommended the granting of small lots of from 25 to 30 acres
to persons employed in constructing the canal who were desirous of
becoming settlers, provided their settlements were 400 yards from the
dams or locks.12
By found that some proprietors eventually altered their opinions
regarding the sale of land to the government and were willing to accept
the true value of their land, instead of asking for ten times its worth,
provided they were allowed to lease such parts of the property as were
not required for the public service.13 The government's main
purpose for retaining the land was to prevent claims for damages as the
canal became enlarged by the wear and tear of steamboats using it. The
government also wished to retain the land in order to prevent the
erection of buildings in the line of fire of defence works which it
might be found necessary to erect in order to protect embankments from
being destroyed by an enemy.14 By was satisfied to lease such
portions as were not required immediately, under such restrictions as to
enable the government to resume the whole at any time it might
require.15 Moreover, in many cases, By was able to make an
advantageous bargain only through purchasing the whole estate and then
granting a 30-year lease to the proprietor who paid the annual rent of 5
per cent on the whole purchase price without any deduction being made
for such portions as were taken for the public service.16 For
example, Allen McLean preferred to accept £2,000 for the whole of
his estate consisting of 2,500 acres instead of the £4,000 he
claimed for damages.17 He was granted a lease of such parts
as were not required for the public service. By cited this bargain with
McLean as an example of the great utility of property on the line of the
Rideau Canal and the objection which proprietors on the line of the
canal had to the possibility of others enjoying the advantages which
they considered to be their right. By found that offering the
proprietors a lease on the said land at moderate terms dissipated
unpleasant feeling and lessened their demands. Indeed he believed that
this practice reduced by one-half the sum the government would otherwise
have had to pay.18
Yet legal disputes did at times occur with landed proprietors wishing
to profit unduly by selling land for the canal. One such dispute with
Nicholas Sparks involved 88 acres of land which By expropriated in the
spring of 1827.19 The greater part of this land was required to form a
reservoir to supply the first eight locks with water, and the remainder
of the land was required to form works for the defence of the said
locks along with wharves, quays and landing places. Section 9 of the
Canal Act declared that "in estimating the claim of any individual to
compensation for property taken, or for damage done under the authority
of this Act, the Arbitrators or Jury assessing such damages shall take
into their consideration, the benefit likely to accrue to such
individual from the construction of the said Canal, by its enhancing the
value of his property or producing other advantages." By learned that
Sparks had purchased from Mr. Burrows in 1823 the land in question,
being part of 200 acres with a small house and £10 worth of
furniture, for the whole of which he paid only £85. Now Sparks was
asking £600 per acre in consequence of the increased valuation
the canal had given to the surrounding area.20
When By first arrived on the site in September, 1826, no improvements
had taken place on this property except the clearing of a few acres and
the building of a smiths' house and shop near the location which By
selected for the entrance of the eight locks. He appraised the house and
shop and offered to give £250 for them and to allow the proprietor
to occupy them for a period of 5 years rent free. But no title to the
buildings was produced and so no purchase took place. Sparks urged By to
pay him for the 88 acres taken for the use of the canal, and By offered
Sparks £1 per acre and payment for all clearing, fencing or
whatever other expenses Sparks may have laid out on such land. Sparks,
however, refused to accept this offer and insisted on receiving
£600 per acre. By declined to give Sparks this amount conceiving
it to be an unreasonable and exorbitant demand. By finally called upon
the attorney general of Upper Canada to defend the action Sparks was
determined to bring against him.21
In standing up to Sparks, By had the full support of Colonel E. W.
Durnford, commanding Royal Engineer in Canada. This officer wrote to the
military secretary on 25 June 1829,
I have to express my regret that Mr. Sparks should have demanded
so enormously for this property when the whole operations that
Government had entrusted Lt. Col. By to execute have been so
prodigiously beneficial to Mr. Sparks as well as most if not all others
from whom property will be of necessity taken in furtherance of the
Rideau Canal. I think it is my duty to make these observations in order,
if His Excellency approves thereof, he may impress them upon the
Committee in any instructions he plans to give
them.22
Whereupon on 2 July the military secretary wrote to Sir John
Colborne, lieutenant governor of Upper Canada:
Adverting to the letter which I had the honor to address to Your
Excellency on the 13th Ultimo, upon the formation of a Committee to
appraise the land required for the Rideau Canal, I am directed by the
Commander of the Forces, to acquaint Your Excellency, that the
Commanding Royal Engineer has nominated Captain Piper as the Officer of
the Royal Engineers recommended to be placed upon that Committee.
I am at the same time commanded to transmit to Your Excellency
copies of reports from the Commanding Engineer and from Lieutenant
Colonel By upon the land belonging to Mr. Sparks acquired for the
service in question the substance of which His Excellency will be
pleased to impress upon the minds of the Committee.23
In another case William Needham claimed for damages for injury to his
land from the Rideau Canal. In this instance, By directed J. Hagerman,
the ordnance solicitor for the Rideau Canal, to write to Needham
desiring to be informed of the lowest terms he was willing to take for
his property, or for compensation for damages occasioned by the rising
of the water in Cataraqui Creek by the dam at Kingston Mills. Needm
asked £800 for the property in question, which By valued at
£400. Later Needham became more exorbitant in his demands stating
that his crop of turnips would produce 4,000 bushels per acre and valued
them at 1s. per bushel. As he had three acres of turnips, according to
his calculation, it would take £600 to pay for that crop alone. On
examining the said three acres, By found that it did not appear that 100
bushels could be obtained off the land. Thereupon By accused Needham of
attempting to impose on the government and said that he would have
nothing more to do with Needham who must lay his claims before a jury at
the completion of the canal as stipulated by the Rideau Canal Act. At
the same time By declared that he considered it to be his duty to settle
Needham's claim the moment Needham would accept an equitable
price.24 Sometime later, Hagerman received from J. Cartwright
of Kingston, solicitor for Needham, a statement of claim for damages to
the amount of £545.12.0. Accompanying the statement was a
certificate from Messrs. Tuttle and Marks, who were acquainted with
Needham's land, stating that the various items listed in the claim were
just and reasonable. Cartwright pointed out that had Needham accepted
By's offer of £400 last fall, it would have been of more actual
benefit to him than the £545.12.0. he was now asking. In
consequence of not receiving satisfaction for his damages, Needham had
been imprisoned upwards of three months, his cattle had been seized and
sold under executions, his family dispersed and his business totally
ruined. He was now in a state of want with demands accumulated by costs
still unsatisfied which he could have settled had he accepted the
settlement in the fall. Needham's lawyer now wished for a settlement
which would pay Needham's debts and secure his release from
prison.25
In July 1831 Colonel By reported to his superiors in Quebec that
there was a piece of land held by Peter Cornish of which Edward McCrae,
the original proprietor, was extremely anxious to assume possession for
the sole reason of claiming heavy damages for the water of the Rideau
Canal overflowing the greater part of it.26 Cornish's power
of purchase would cease next September unless it was completed by that
time. But Cornish had not the means of completing the purchase and had
offered it to the ordnance for £150. By proposed that the
ordnance should purchase from Cornish in order to prevent McCrae from
bringing an action against the government for damages, and this was
done.27
The Royal Navy was also among the claimants for damages. In 1830
Commodore Barrie at Kingston wrote to By that "the Naval Department will
look to the Ordnance Department for the Payment of all damages done to
the said property (at Kingston Mills) by the Ordnance
Department."28
Lands taken for the Rideau Canal could not be let or leased without
the concurrence of the commander of the forces or the ordnance officers
at Quebec. In one case, lots Nos. 34, 35, 36, 37 and parts of 39 and 40
containing about 1,000 acres were purchased from Cornelius Phillips in the
township of North Cower for the sum of £200. Ordnance then
requested permission to let to James, Patrick, Edmond and Michael
Murphy, for the sum of 12s. per annum as a rent for 60 acres of the
land now shared and a further sum of 1s. per annum for every acre which
might hereafter be cleared at their expense. Ordnance believed that
this arrangement was for the benefit of the government.29
Sometimes By became involved in legal disputes when removing
intruders from lands of which he had taken possession. The question
was: How much land could he take? The attorney general of Upper Canada
filed writs of Information of Intention, until the right be determined
in a court of law, against persons who repossessed themselves of lands
set apart and required, in By's opinion, for the use of the canal. He
desired to take lands at certain points in order to fortify the canal
and the attorney general maintained that if By would in the words of
the Rideau Canal Act "set out and ascertain" some given site where he
thought such a work most necessary, and taking as little ground as
possible, then he, the attorney general, would file an Information for
By against any person who intruded upon it.30
ii
The construction of the Ottawa canals led to claims for damages from
property owners adjacent to them. By virtue of an order in council
passed in 1829, the Crown resumed additional land at the
Carillon.31 The whole area between the canal and the river
was taken in order to prevent obstructions and nuisances in the vicinity
of the locks. However, no more land was taken from the proprietors than
was necessary for the purposes of the canal and no land was
taken which might be required for purposes of defence. Quite
naturally demands for compensation arose from the proprietors of the
resumed lands. The government therefore appointed Mr. Brown of
Beauharnois to act as its arbitrator in settling the
claims.32 He visited the Carillon in October, 1830, where he
met with considerable hostility from the closely knit group of local
proprietors mutually determined to extract excessive compensation from
the government. Brown thereupon deemed it useless to proceed any further
in his attempt to arrive at an equitable settlement of claims and
promptly left the scene.33 In the following year a fresh
order in council was passed for the resumption of such land as was
required but not sanctioned by the former order, as well as for the
relinquishment of such land as was before included but was not now
required. Renewed demands for compensation were now made by the
proprietors who entered a suit for damages in the Court of Kings Bench
at Montreal. Whereupon the court ordered an arbitration of the dispute
and in the spring of 1832 the proprietors obtained a favourable
judgement.34
Tedious and protracted claims for damages were forthcoming from the
proprietors at the Chute-à-Blondeau. Simon Fraser of Terrebonne claimed
for damages done to his property by the construction of the
canal.35 Concomitant claims were also made by James Fuller
and Solomon French who had purchased lots from Fraser. In October,
1830, Mr. Brown, following his unsuccessful attempt at arbitration at
the Carillon, accompanied Colonel DuVernet, commander of the Ottawa
canals, to the Chute-à-Blondeau, where he met with Solomon French.
French's demand for compensation appeared to Brown unreasonable and, being unable to
find an impartial person on the spot to call as a third arbiter, he
suspended the whole business.36 In 1834 the ordnance
paymaster of the Ottawa canals informed Fraser that the government was
ready to pay him and the other two gentlemen the sum of £129.12.6
for the land.37 Fuller and French, however, were
really more interested than Fraser in this final settlement, and they
would not agree to so small a sum as compensation for the loss they had
sustained.38 Thereupon, Fraser, after consulting with Fuller
and French, decided not to accept the money offered by the ordnance
paymaster believing that to do so would make him liable in action for
damages to Messrs. Fuller and French for injury done to their
property.39 Fraser decided to submit the matter once again to
the governor-in-chief.40 A few months later in March, 1835,
Fuller expressed his case in a letter to the ordnance
office.41 He had had his mill site examined several times by
competent persons who had estimated it as worth £2,000. At one
time he had built a lime kiln and had made preparations for building a
mill. This work, however, had been suspended in consequence of the
construction of the canal. He therefore had to construct these works at
another location where his trade was confined and crippled through lack
of water. Construction of the canal had thus broken up his mill and tan
works. After stipulating what he was ready to accept in the way of
compensation, Fuller went on to say that had the Ottawa canals been used
exclusively for "military works of defence, he should have little to
say, but it was notorious that these canals were used by the government
for purposes of trade and profit."42 He expressed his
belief that "no Court of Justice under the Crown would
permit the property of the subject to be taken from him and applied to
such uses."43 The matter should, according to Fuller, undergo
a proper legal investigation and the question be decided upon by a jury.
Fraser could not dispose of or compromise Fuller's rights nor had
Fraser received any money for the land taken at the Chute-à-Blondeau.
This fact continued to perplex the authorities. On 15 May 1835,44
Colonel Nicolls, commanding Royal Engineer in Canada, informed the
commander-in-chief of the forces that though Simon Fraser had been
notified several times that payment for the land taken by the Crown was
awaiting him, he had not yet called upon the ordnance paymaster to
receive it.
There was also a claim regarding the Grenville Canal from a
proprietor, Claude Greece.45 On 10 June 1829, this gentleman
complained to Colonel DuVernet, commanding officer of the Ottawa
canals, that the water from the canal leaked through the banks so as to
cause the destruction of his crops and to render useless a considerable
and valuable area of land. When Greece first detected the leakage he set
about cutting temporary drains which did not help much, and as a result
aquatic weeds soon grew where formerly had been crops of wheat. Greece
complained that other parts of his land, which were previously sound and
dry, were now always under water whenever the canal was full. He said
that this injurious effect often attended canals unless very great care
was taken in the formation of their banks. He maintained that it was
customary in England for those who constructed canals to secure, by
ditches parallel to them, the property of the persons through whose
lands they passed. Greece, however,
found that little was being done by Colonel DuVernet to remedy the
situation. He therefore placed his complaint before Lord Aylmer stating
that "although the Crown has a reserved Right for Military Canals, that
the King's subject may not materially suffer through their leakage, and
that Your Lordship will be pleased to permit that some competent and
impartial person do in the opening of the season inspect the damage
complained of, and order such relief by Drainage or otherwise as the
circumstances require." Colonel DuVernet's opinion, based on his knowledge of
the ground and the survey taken before the canal was cut, was that the
annoyance Greece complained of did not altogether result from the
leakage of the canal bank but from the natural lowness of the land. He
actually believed the Greece property, as well as that of the other
proprietors similarly situated along the Grenville Canal, must be
greatly improved rather than injured by the said canal.46
Greece died shortly following his petition to Aylmer, whereupon his
heirs made a claim, which seems to have been granted, for a considerable
piece of vacant land in compensation for that which they maintained the
canal rendered unfit for agriculture.
iii
"An Act for making a Navigable Canal from the neighbourhood of
Montreal to the parish of Lachine" (1 Geo. IV, C.6),47
provided for the appointment of commissioners to superintend the
construction of the work. Once appointed the commissioners lost no time
in choosing a committee to confer, at Côte St. Paul, with the
proprietors along the line of the canal regarding the purchase of land
required for the waterway.48 On 8 June 1821, the committee
reported that the proprietors would propose no price but would willingly agree to the
appointment of arbitrators to make an evaluation of such
grounds.49 Three days later, the proprietors came to the
canal office and the arbitrators for evaluation of their grounds were
then appointed: Hugh Brodie and Paschal LaChappelle on the part of the
canal commissioners, and Joseph Alard and James Milne on the part of the
proprietors.50 These gentlemen were farmers, resident in the
parishes of Montreal and Lachine, and not interested in any lands
through which the canal was to pass. The arbitrators were empowered to
appoint an umpire. It was agreed that once the arbitrators were
appointed both parties would abide by their award and that of the umpire
in cases wherein they might differ in opinion.51
On 14 June 1821, a meeting took place at Lachine of the
commissioners, secretary, engineer, proprietors of land and the
arbitrators. On this occasion the arbitrators chose N. B. Doucet, notary
public, as umpire.52 The commissioners suggested that the
first task of the arbitrators was to define the evaluations of damages
which might be incurred by needful removal of buildings, orchards,
gardens or some other cause.53 Persons present at this
meeting went to view the proposed line of the canal by Côte St. Paul
where the arbitrators began their examination of the several properties
pointed out to them. Once made, the award or decision of the arbitrators
for evaluation of the ground was transmitted to the Court of King's
Bench, as directed by the Act.54 The decision was also
conveyed to the interested proprietor.
Early in August the proprietors made applications for payment of
lands to be taken for the canal. The engineer was
directed to make a return of the breadth of each man's property.
Meantime part payment was to be made leaving the residue of payment
until the canal should be completed and the precise quantities of ground
finally required and taken were ascertained.55
Though the commissioners believed that the arbitrators had acted
conscientiously in their valuations, these were higher than had been
expected.56 Even so, some proprietors were so selfish and
greedy that they expressed dissatisfaction with the appraisal of their
lands. Whereupon the commissioners became alarmed at the probable
magnitude of the claims and awards which might be made for the value of the
property. The commissioners believed that the proprietors "would be
awarded too much as the current of feeling runs too strongly in favor of
claimants, at the expense of the public interests."57
The first projection of the Lachine Canal had intended to place the
terminus at the foot of the current Ste. Marie with a branch running
from the main line to a point on the river near the actual entrance.
But the prices asked for land were at the time considered so exorbitant
that it was deemed necessary to shorten the canal and change the
location of the terminus. This was done by the Act cited above (1 Geo.
IV, C.6). Yet the importance of continuing the canal to the lower
location was so apparent that two years later, in 1823, an Act was
passed which directed that measures should be taken to ascertain the
value of the land required in obedience to this Act.58 The
canal commissioners then appointed Messrs. Julius Quesnel and Thomas
Phillips commissioners to obtain the required information.59
These gentlemen reported that the proposed extension would pass
through 87 different properties; that the value of the land amounted
to £12,547, and the value of the houses amounted to £3,821
making in all £16,368. They strongly urged the purchase of the
land with a view to future extension of the canal.60 The
suggestion, however, was not carried out.
Through their inflated prices for land, some of the proprietors,
therefore, determined the eventual route of the Lachine Canal. As
finally constructed, the lower entrance was comparatively high up the
river near the foot of the rapids with a swift current to be overcome
before it could be reached and entered. Had the canal been extended to
some 2-1/4 miles below the final terminus to the foot of St. Mary's
current, as was originally intended, the canal would have entered into a
body of still water and the whole Port of Montreal, instead of lying in
a current as it did when the Lachine Canal was finally completed, would
have possessed an improved body of water.61
iv
By the provisions of the Act incorporating "The Welland Canal
Company" (4 Geo. IV, C.17),62 the directors of the company were
empowered to contract, compound, compromise and agree, with the
owners and occupiers of any land through or upon which they may
determine to cut and construct the said intended Canal, with all
necessary and convenient locks, towing-paths and other erections and
constructions contemplated by this Act, to be cut, erected, constructed
and built, either for the absolute purchase of so much of the said land
as they shall require for the purposes of the said Company, or for the
damages which he, she or they, shall and may be entitled
to recover from the said company in consequence of said intended
canal.
No sooner had construction begun than claims for damages
poured in to the company from proprietors along the course of the canal
from the Welland River to Lake Ontario.63 Thereupon, in
accordance with the provisions of the Act passed on 30 January 1826 (7
Geo. IV, C.19),64 an arbitration was held at St. Catharines in August
of that year to determine the amount of damages to be paid by the
company. With the exception of a very few individuals (one and only one
claim was quickly settled for the sum of £600), all persons with
claims in respect to that portion of the canal from the Welland River to
Lake Ontario submitted them to the arbitrators. The final award
directed the company to pay damages amounting on the whole to
£1,794.65
Meantime the directors of the company had applied to the lieutenant
governor for a grant of crown land comprising roughly 13,000 acres in
the township of Wainfleet on that part of the canal which was to connect
the Grand River with the Welland. In their memorial for this grant of
land the directors pointed out that thus far the British government had
given no support to their undertaking, whereas the granting of the
petition would not only indicate the interest that the imperial
government took in the canal company's success but would also increase
the value of the company's stock, thereby making it easier to sell. The
directors also pointed out in their memorial that the value of landed
property to the west of the projected canal would increase and the
Crown, with lands in that area, would benefit.66 Whereupon
the lieutenant governor, at the solicitation of the directors, forwarded
to Lord Bathurst the memorial for the grant of an extensive tract of
land. The final grant of 13,400 acres proved to be most fortunately
situated, the line of canal running nearly through the centre of
it.67
Finally, the Act of 20 January 1826 stipulated how the value of any
mill site which the company required to purchase would be ascertained
in the event of disagreement between company and proprietor. In such a
case arbitrators were to be appointed and these would not only assess
the value of the mill site but were empowered to decide whether the
person owning the site could be compelled to part with it to the
company.
v
The Chambly Canal, in permitting water communication between Lake
Champlain and the St. Lawrence River at Sorel, was an important part of
the St. Lawrence waterway. From 1787 on, commercial and political
reasons were advanced for the construction of this canal;68
to these, the War of 1812 added a military one. Finally in 1827 the
Province of Lower Canada made an appropriation for improving the Richelieu
navigation and undertook the work itself.69 Commissioners
were appointed in 1829 to carry out the scheme70 and the
following year work was commenced at St. Ours, 14 miles above Sorel.
Once appointed, the chairman of the Board of Commissioners for the
Chambly Canal transmitted to the commander of the forces a plan for that
portion of the government ground at Chambly that would be required for
the canal.71 Whereupon the commander of the forces requested
the commanding Royal Engineer in Canada to send an officer of his
department to Chambly to contact the commissioners for determining the
boundaries of land belonging to the Crown which
would be required for the proposed canal.72 This land had
actually been transferred to the Board of Ordnance and was in the
keeping and custody of the board's officers of which the commanding
Royal Engineer in Canada was one.73 The engineer officer sent
to contact the commissioners was to delineate the land required for the
proposed canal, on the plan furnished by the commissioners, for the
approval of the commander of the forces. This was done and the required
land placed at the disposal of the canal commissioners.74
From then till 1841, work on this canal was carried on in a very
unsystematic way and it remained for the Board of Works, formed after the
union, to complete the undertaking.
II
i
The awarding of contracts to persons prepared to undertake the work
was an important aspect of canal construction. The spring of 1827 found
Colonel By in Montreal busily engaged in this task. Local newspapers
carried a notice explaining how the awarding of contracts was to be
done. "It is best to allow no contractor to have anything to do with
them (the Works) be his cash or consequence what they may, unless he is
well known as a practical artist, competent for what he
professes."75 The notice also summarized the work to be done
as follows: "The works of the Rideau Canal seem to divide themselves
into the following great branches; building and finishing of locks of
heavy masonry; framing aqueducts and bridges of wood." The government,
it was further explained, would supply spirits, provisions and camp
equipment; engage surgeons furnished with necessary medicines, and
station a subaltern's command of 60 soldiers near each contract work.76
Each contract was an agreement between the commissary general of His
Majesty's forces in Canada, for and on behalf of the Crown, and the
named contractor who guaranteed to carry out the stipulated work for the
unit sums noted in the document. In one contract the unit prices were
4s. per cubic yard for rock evacuation and 1s. per cubic yard for earth.
The contractor was paid these prices for each of the units noted.
Engineers would measure the total amount of work completed and the
quantity multiplied by the unit price would give the total due the
contractor. The contractors on the Rideau Canal and elsewhere, instead of
receiving cash, accepted drafts on Montreal which they disposed of at a
premium for bank notes, the drafts being payable in dollars on
presentation.77 Prior to leaving Montreal in the spring of
1827 to take up his residence on the bank of the Ottawa, By had the
satisfaction of knowing that all the main contracts had been awarded.
The minor ones that remained were granted by the middle of the
summer.78
During the summer of 1827 actual work was started on the canal. By
informed General Mann that he had a good portion of the work contracted
for at moderate prices.79 He allowed no man to contract for
more work than he could execute in three years.80 Mr.
Pennyfether had contracted to excavate the first eight locks from the
Ottawa River and to complete the work by 1 August 1827; however, it was
found impracticable to finish the excavation by that time due to a
great number of springs which created more work and consequently an
unavoidable delay.81 Thomas Mackay, the practical man who
built the locks in the Lachine Canal, contracted to build the masonry of the first eight
locks and to complete them in two years from the date of signing the
contract. However, he too was unable to finish them in that time due to
the same unavoidable cause as Mr. Pennyfether's.82 Mr.
Fenelon contracted to clear and excavate the canal from the first eight
locks to the north side of Dows Great Swamp. He also contracted to
excavate and form the canal from Dows Great Swamp to the Hog's Back,
chiefly rock excavation, forming an aqueduct bridge 20 feet long across
Peters Gully, excavating and constructing three locks each of 10 feet
lift, and forming a dam of arched key work across the Rideau River 240
feet wide and 40 feet high.83 This dam was to convert 7 miles
of rapids into a sheet of still water and thereby save the expense of
excavating the canal for that distance. Mr. Henderson contracted to cut
a drain from the Beaver Meadow to the Rideau River to drain the swamps
through which the canal had to pass. This work was expected to be
completed in August. This gentleman also contracted to form a mound of
earth across Dows Great Swamp and to construct the canal on the top of
this mound.84 Mr. Phillips, a Montreal mason, opened
quarries at the foot of the Black Rapids in order to construct a dam
across the Rideau River 280 feet wide, 10 feet high and a lock of 10
feet lift. This dam would throw back the water and form a sheet of
still water 5 miles long which would complete the canal to the foot of
Long Island Rapids where By proposed to construct locks of 8 feet lift
each and a dam across the Rideau 158 feet wide and 24 feet high. This
would throw back the water 3 miles, convert that length of rapid into
still water and give an uninterrupted navigation
for 23 miles to Colonel Burritt's house on the banks of the Rideau 44
miles from the Ottawa and 144 feet above the river.85
By also informed Mann that he intended to perform by day-work, and
under the immediate supervision of himself and his officers, all the
piling of the foundations and laying of the stones forming the
coffer-dams and waste weirs. He reported that the large blocks of hard
grey limestone, granite and sandstone that the various quarries produced
would enable him to erect both desirable and ornamental works. In
conclusion By expressed his anxious waiting for the arrival of the second
company of Royal Sappers and Miners.86 Two companies had
been raised in England especially for work on the canal, each
consisting of 81 men. The 15th company arrived on the site on 1 June
1827; the 7th company on 17 September. These two companies were amply
employed in constructing lock gates, sluices, waste weirs and stone
bridges across the canal.
22 Plan of the proposed route of the Welland ship canal.
(Sessional Paper No. 20, 1914.) (click on image for a PDF version)
|
23 The Sault Ste. Marie Canal and locks. From the
Dominion Illustrated, 22 August 1891.
(Public Archives of Canada.)
|
In March 1828 By received from General Mann a letter suggesting that
he try to prevent as far as possible incurring any expense upon the
canal beyond what it had been intended to grant in that year, and to
limit his engagements in contracts.87 The letter did not
reach By, however, before all the contracts for the masonry of various
locks, the construction of the different dams, and the clearing,
grubbing and excavating had been accepted and closed by the deputy
commissary general at Montreal on 1 February. Up to now, By had acted on
the assumption that he should press the work to the utmost. Upon
receiving Mann's letter he discharged all his civilian carpenters,
smiths, labourers and squad masters. At the same time, he
asked the contractors not to increase their expenditures while
promising to prolong the period for completing the contracts. The
contractors, however, resisted this idea. By feared that there would be
great difficulty in getting the contractors to slow down for they
believed that the quicker they did the work the greater their profit. When
By suggested that they take a longer time to complete their contracts,
the contractors replied that they could finish them in one year but
that if they were interrupted they would incur great losses and should
therefore demand damages. By, however, was not unduly alarmed by this
threat. He felt that most of the contractors would find it difficult
enough to execute all the works they had undertaken in the time allowed
them by their contracts.88 He decided that not to give them
any pretence for delaying the work, as by so doing they would claim
damages, would be the surest way of keeping down the expense. He
reasoned that by withholding his issues of cash strictly to the terms of
their contracts, the contractors would not proceed as rapidly as they
had intended.89
Contracts awarded for the work were prepared by the Commissariat
Department at Quebec and not by Colonel By. He had no control over the
amount of work done by the contractors each year. The contracts provided
that the contractors should be paid as the work progressed on a unit
basis, that is to say, so much per cubic yard for excavating earth or
rock. The masonry work in connection with the locks and the dams was
similarly treated. Many of the contractors discovered that their
figures were much too low, and in consequence found they were losing
money and discontinued their contracts, thus causing delay. Or, By
would have to remove them from the project they had started because of unsatisfactory
progress. Though the provisions in the contract clearly spelled out the
contractor's responsibility, yet By was continually besieged by those
who had failed, or by their creditors.90
ii
In July, 1825, construction on the Welland Canal was begun in
earnest after agreements were signed with the contractors which called
for the completion of the Welland River-Lake Ontario section by August,
1827. Two months later work was begun on the Deep Cut, and by the end
of 1825 excavation was in progress at a number of points along
the line. Following are the names of the original contractors on the
Welland Canal with their sections.91 These were numbered
from the Welland River and varied in length according to the depth of
cutting and amount of work. At first the directors had complete
confidence in the contractors who were described as being "persons as
eligible in all respects as they think the Board could have met with. .
. . They have exhibited a knowledge of their several descriptions of
work and have practised to this time a regularity, economy and a
persevering industry in the conduct of it, which it is believed have not
often been excelled."92 It was not long, however, before the
directors were to learn that such overwhelming confidence was in some
cases badly misplaced.
|
Sections | Contractors |
|
No 1, 2, 3, 4, 5, 6 (the Deep Cut) | Messrs. Beach, Ward and Hovey |
|
7 | Kennedy and Company |
|
8 | James Simpson |
|
9, 10 | Hall Davis |
|
11, 12, 15,16, 20, 24, 25 | Wallace Bell, Thomas Griffiths, William Richardson, Nicholas Walton, Joseph Carr |
|
13 | William Simpson |
|
14, 17, 18,19, 21, 22 | John Gooding, Levi Taylor, Richard Hathaway, ______ Sayer |
|
23 | James Simpson |
|
26, 27 | Davis and Simpson |
|
28 | Hannan and Company |
|
29, 30 | Houg and Company |
|
31 | Davis and Simpson |
|
32 | Gooding, Houg, Biglow and Jones |
|
33 | Porter and Donaldson |
|
34 | John Tembrock |
|
35 | Beach, Ward and Hovey |
|
The Harbour | Beach, Ward and Hovey |
|
The Locks | Oliver Philps and Company |
|
It was perceived in the early stages of construction that to proceed
with the dispatch which the contractors pressed upon the company, and
which it was evidently the interest of the latter to facilitate, would
demand a larger expenditure than could be provided for from the existing
funds. At the same time it was strongly urged upon the directors by the
principal stockholders that no necessary expense should be spared in
procuring engineers "of competent ability and of known character."
Accordingly, early in the season of 1826, Alfred Barrett, long employed
on the Erie Canal, was engaged as the principal resident engineer under
whose immediate and constant superintendence the whole of the work
proceeded. David Thomas, the principal engineer, was engaged at an
annual salary to visit and report on the state and progress of the work
and to suggest any improvements on the original design.93
During 1826 considerable progress was made. By October, 330,704 cubic
yards had been excavated out of an estimated total of 1,457,238, and
202,707 yards of embarkment had been completed leaving 155,445 yards
still to be constructed. Of the first section which commenced at the
Welland River and was 66 chains in length, one-half was completed, the
towing path finished and the water let in. The second, third, fourth,
fifth and sixth sections formed the Deep Cut where the greater part of
the labour force was concentrated. Here just under half of the
excavation was completed and bottom land had been reached at one point.
On the 5-mile section descending the escarpment, four locks were
completed by the end of the year except for their gates. It
was believed that the St. Catharines-Lake Ontario section with the
layer locks would be navigable during the following season. The full
amount of capital stock not being subscribed, the directors at this time
did not proceed to contract for the western section of the canal leading
from the Welland to the Grand River. Later, however, as the necessary
funds became available, the directors let contracts for that part of
the work since it was apparent that neither the company nor the public
would reap the full benefit of the Welland project until that part of
the canal was finished.94
By September, 1827, work was so far advanced on the northern, or Lake
Ontario-Welland River section, and the necessary funds being available,
tenders were called for the southern or Grand River section. Contracts
for this section were let to Messrs. Manson, Simpson and Company on 4
October, and a beginning was made on the slow job of draining the swamp.
By December, however, work on this section was halted through financial
difficulties but not before 72,000 cubic yards of earth had been removed
and drainage ditches carried into the swamp for three or four
miles.95 Meanwhile the American contractors who had
undertaken the Deep Cut, Messrs. Beach, Ward and Hovey, expressed their
inability to carry on the work any further at the contract price. They
were bankrupt and could not possibly meet the specified date for
completion.96 At the same time, the section from St. Catharines
to Lake Ontario was already in use. Only the Deep Cut remained
unfinished and was the one obstacle to the completion of the canal.
When the 1828 season opened all energies were concentrated on the
Deep Cut. Philps the contractor and Barrett the engineer recommenced
the work late in April. By October two sections of the cutting were
completed.97 If the Deep Cut could be finished by the end of
the year, then the first two sections of the canal from Lake Ontario to
the Niagara River could be opened for traffic in 1829. However, suddenly
on 9 November the banks of the Deep Cut collapsed. This disaster meant a
complete stoppage of work. The real source of trouble lay in the fact
that excavation of the bottom of the cutting had reached a bed of loose
sand and as soon as the level was reached and water allowed to enter,
the sand was carried away in the form of silt and the high banks were
undermined.98
The original plan for the canal had now to be changed. Instead of
using the Welland River as a feeder, which necessitated lowering the
level of the Deep Cut to the level of that river, now impossible because
of the sand, a new feeder had to be found to bring in a supply of water
at a higher level, thus enabling the bottom level of the Deep Cut to be
raised. The directors now called upon James Geddes, an experienced
engineer, for assistance, and he along with Barrett ran new surveys in
November and December. The engineers found the key to the situation in
the Grand River section which depended on Lake Erie, not the Welland
River, for its water supply. However, the level of the Lake Erie above
the sand level in the Deep Cut was not sufficient to give the desired
8-foot level, even if the feeder were brought in directly from the lake.
In their reports submitted early in 1829 the engineers, therefore,
proposed to build a dam across the mouth of the Grand River to raise
the water 5 feet above Lake Erie. Then a long cutting could be made
direct from this reservoir to the Deep Cut passing over the Welland
River, the original feeder, by an aqueduct. They could by this
plan bring in a supply of water to provide a depth of 8 feet in the Deep
Cut. Henceforth the whole canal from the mouth of the Twelve Mile Creek
to the Grand River estuary would be from the hydraulic point of view one
system, the effective operation of which depended primarily on the
Grand River dam, the long feeder from Grand River to the Deep Cut, and
the aqueduct over the Welland River. The new plan necessitated
additional locks at each end of the Deep Cut, two at the south end to
enable vessels to pass from the canal to the Welland River and two at
the north end to connect the new higher level in the Deep Cut with the
old level from that point to Lake Ontario.99
On 31 January 1829, the new feeder line extending from the Deep Cut
to the Grand River was put under contract. But construction did not
begin until early in May. Work on the final location of the Grand River
dam began early in June. Progress on the line of the feeder was delayed
by illness among the labourers in the marsh sections. These delays were
a serious matter. The company was near the end of its financial
resources and the provincial government would extend financial
assistance only if the canal was open for traffic in the following
season. Meanwhile work was carried on by hasty makeshift credit
arrangements. "Each contractor agreed to accept partial payment for work
done in proportion to the means at the disposal of the company. Normal
contracting procedure was discarded to permit concentration of labor and
equipment on sections where the work was lagging, particularly on the
line of the Grand River feeder."100 On 30 November, two
schooners finally passed through the canal from Lake Ontario to Buffalo
Harbor.101
This passage, however, was symbolic only. Much work yet remained to
be done on the canal. Especially was this the case in respect to its
wooden locks, some few of which were badly constructed in the first
place owing to fraud on the part of the contractors.
iii
The commissioners responsible for the construction of the Lachine
Canal were appointed on 26 May 1821.102 They took the first step
toward the execution of their duties with the nomination of Mr.
Richardson as their chairman on 4 June. A week later, the commissioners
inserted in the newspapers an advertisement for contractors to
excavate the canal allowing until 30 June for submitting tenders, which
time was afterwards extended to 5 July.103 On 25 June, Thomas
Phillips, one of the commissioners, stated that he would tender for the
excavation contract and he therefore wished to resign, it being
distinctly understood that no person acting as a commissioner could,
directly or indirectly, become a contractor. Phillips' resignation was
immediately accepted by the commissioners and he was allowed to
tender the same as any other person.104
On 6 July the tenders for excavation were opened. Explanations of
some points not sufficiently explicit were found to be necessary. Such
explanations being made, the proposals of Andrew White, Stanley Bagg,
Thomas Phillips and Oliver Wait, with the offer of John Fry and Abner
Bagg as their securities, were accepted for the whole line of the
canal. The rates were as follows:105
Excavation in earth of all descriptions | 8-1/2d. per cu. yd. |
Extra-cutting in earth of all descriptions | 7d. per cu. yd. |
Excavation in rock of all descriptions | 3s. 3d. per cu. yd. |
Extra-cutting in rock of all descriptions | 3s. per cu. yd. |
"Extra-cutting" meant what was done, whether in rock or earth, above
the level of the towing path of the canal.
The commissioners found that although some of the tenders had
apparently lower costs, they were for short distances where there was no
rock, and consequently putting the price at a low rate had no
substantial practical meaning. The object of the commissioners was to
obtain firm prices for the whole work, including the different
descriptions of it, in order to know what the total cost would be. They
also wished to avoid, if possible, any collision and dispute likely to
result from a variety of unconnected contractors.106
Those who had taken the excavation contract were persons of
considerable property and so were their securities. The contract
stipulated that the contractors undertook all risks and expenses arising
from water getting into the works or other accidents. Upon the same
principle, a contract was afterwards made with the contractors, it
having been previously advertised, for making fences between the canal
and contiguous grounds in order to protect those grounds from injury and
to protect the commissioners against claims for damage thereto. The cost
of this fence according to a prescribed specification of its height,
materials and mode of construction was 50 shillings per arpent in
length, including gates, and keeping the same in repairs until the canal
was finished.107
24 A whaleback type of vessel for bulk cargo transport in the Sault
Ste. Marie canal. This class of ship originated in the Great Lakes.
(Public Archives of Canada.)
|
25 Locks at Sault Ste. Marie, about 1897.
(Public Archives of Canada.)
|
On 15 October, an advertisement was published for tenders to be made
on or before 17 November for furnishing stones fit for the locks.
However, information having been obtained that there was a quantity of
stone at Caughnawaga of excellent quality, the engineer was directed to
examine the same and, his report being favourable, measures were taken
for obtaining His Excellency's consent to procure that stone on the
usual terms, it being upon the property of the Indians. This occasioned
some delay and consequent alteration in tenders, the original ones
planning to use the quarries near Montreal.108
The commissioners finally accepted the tender of Thomas MacKay, a
professional stone-cutter and mason, with James Leslie as his security,
at the rate of 5-1/2d. per cubic foot of gray stone, fit for
cutting, deliverable at the quarry for different kinds required for the
locks, and 30s. per toise for stones adopted for the foundations
and the backing; reserving for the excavation contractors the right of
furnishing according to agreement such stone applicable to locks as
should be found in the bed of the canal upon payment to them at the same
rate as to the stone contractor, and deducting therefrom the allowance
they received for excavation of rock.109
Excavation proceeded rapidly in summer but it was not practicable
to proceed with it in winter. The quarrying and cutting of stone at
Caughnawaga, however, went on during the winter.110
When the canal was opened for traffic in August, 1824, the contractor
for cutting the stone claimed a large balance due him which the
commissioners refused to pay. Thereupon the matter in dispute was
referred to arbitration. The contractor's accounts for quarrying and
cutting the stone were handed over to
the arbitrators who gave as their award that the sum of
£501.12.4 was to be deducted from the contractor's claim leaving a
balance due him of £2,079.1.5 toward finishing the locks,
building houses for the toll collectors and completing other necessary
works.111
iv
A word might be said about the contracting for repair work to be
done on the military canals along the St. Lawrence. The British
government owned these canals, received revenue from them and had the
responsibility of keeping them in repair.112 In this matter,
however, friction developed between the commissary and engineer
departments. The system of placing the military canals at Coteau du Lac,
Split Rock and the Cascades in the charge of the commissariat while the
responsibility for their good repair was thrown on the engineer
department was bad in theory and worse in practice. It was the source of
keeping the two departments in continual conflict for many
years.113 In 1832 the captain of Royal Engineers in Montreal
complained of being treated as a subordinate officer by the deputy
commissary general there. And the following year the commanding Royal
Engineer in Canada at Quebec complained of being treated in a similar
manner by the commissary general. From the commanding Royal Engineer's
point of view, the only solution was for the commander of the forces to
direct the commissary general to have all the estimates executed under
commissariat on the canals, along with their revenues and repairs, put
entirely into the hands of the ordnance like those of the Rideau and
Ottawa.114
Some military authorities in Canada believed that the provincial
legislature of Lower Canada might be disposed to
consider a proposal for purchasing these canals. These same
authorities, however, also believed that the province's offer to
purchase would not amount to more than £15,000 a sum
bearing no relation to their value or revenue which was about
£2,500 annually in 1832 and increasing rapidly.115 The
only way by which the British government might have effected this
transfer at less sacrifice would have been in the settlement of any
outstanding account wherein the Province of Lower Canada might have had
a claim against the British government and consented to receive these
canals in payment at a fair valuation.116
v
In his speech at the opening of the session on 4 February 1817, the
lieutenant governor of Upper Canada urged that the water communication
below Prescott deserved the serious consideration of the
legislature.117 The following year a joint commission,
consisting of Messrs. Thomas Clark and James Crooks for Upper Canada and
Messrs. George Gordon and Joseph Papineau for Lower Canada, reported
that improvements were necessary at several places along the St.
Lawrence. They recommended that canals should be built with dimensions
of not less than 90 feet long by 12 feet breadth in the clear at an
estimated cost of $600,000.118
In 1826, the lieutenant governor of Upper Canada transmitted to the
legislature a report on the subject made by Samuel Clowes119
Four years later another examination of the inland navigation was made
by Alfred Barrett who reported that all the obstructions existing to
the navigation between Lake St. Francis and Lake Ontario might be
removed so as to allow the passage of
Durham boats drawing four feet of water for the sum of £45,198
($180,792) and of steamboats and schooners for the sum of
£173,648 ($694,592).120
In 1832 the House of Assembly of Upper Canada resolved "That the
public interest requires that the navigation of the River St. Lawrence
should be improved so as to admit of navigation by vessels drawing nine
feet of water, and that it is expedient to commence such improvements
with as little delay as practicable, between Cornwall and the head of
the Long Sault Rapids."121 Accordingly a Bill was passed
appropriating the sum of £90,000 ($280,000). In 1833 a commission
was appointed to carry out this project.122 Benjamin Wright
was employed as principal engineer and John B. Mills as his assistant.
One of the conditions of the Act was that the Cornwall Canal should be
commenced and finished before any of the other projected works leading
to Lake Ontario should be undertaken.123 Wright was also
employed by the government of Lower Canada to make the survey of the
lower canals on a scale to correspond with the canals surveyed for
Upper Canada.
In 1833 these engineers reported that the following canals were
necessary for establishing a communication between Lakes St. Francis and
Ontario: Long Sault (Cornwall Canal), Farran's Point, Rapide Plat, Point
Cardinal and Les Galops. The estimated cost for the construction was
£323,616 ($1,294,464). Adding to this the cost of the land, the
estimated cost in round numbers was £350,000 (1.4
million).124
Commissioners appointed to superintend the construction of the
Cornwall Canal hired Benjamin Wright as consulting engineer and J. B.
Mills as resident engineer. The professional services
of Captain Cole, R.E., and of Messrs. Geddes and Fleming were also
retained. Tenders were received on 6 July 1834, and the construction
undertaken at various rates.125 The following year the
price of labour and provisions had risen so high that the commissioners
were induced to add 10 per cent to the prices agreed upon with the
contractors. And in 1836, owing to the same causes, the additional
allowance was increased to 30 per cent.126 In that year,
Mills, the resident engineer, resigned and Captain Phillpotts, R.E.,
was appointed in his place. The next three years were difficult ones
for the canal commissioners. Political unrest, commercial depression and
exorbitant demands for damages to property resulted in the suspension of
construction and the discharge of professional personnel connected with
the engineer's department.
In his general report on inland navigation in 1839, Phillpotts
estimated the cost of completing the Cornwall Canal at £57,300
($278,860).127 At the time of union, the estimated expenditure on this
canal up to 31 December 1838 amounted to £354,203 ($1,416,812)
and, it was believed that a further sum of £57,671 ($230,685) was
required to complete the works.128
vi
In the years immediately following the War of 1812, the necessity of
opening a water communication between the St. Lawrence River and Lake
Champlain was fully discussed. In 1818 the legislature of Lower Canada
passed a Bill granting to a company the right of forming a canal so as
to connect the navigation of the lake with the basin at Chambly and
avoid the Chambly rapids. The Act prescribed that the locks should not
be less than 20 feet in breadth and
of a sufficient depth to admit vessels drawing 5 feet of water. The
company's capital was limited to £45,000 ($180,000) and the canal
was to be completed with in seven years.129 Thereupon the
company ordered the necessary surveys and designs and informed the
legislature that the cost of construction would far exceed the capital
authorized to be raised for the purpose. Hence the company asked for
authority to increase its capital. By 1823 construction had still not
yet begun and it was clear that the company would forfeit its rights
under the clause in their Act which prescribed that the canal should be
completed within seven years. A new Act was therefore passed
appropriating £50,000 ($200,000) for the construction of the
canal.130 Commissioners were finally appointed in 1829;131
necessary surveys were immediately proceeded with, and in October, 1831,
the works were commenced by contractors who undertook the whole for
£46,218 ($184,872). As it turned out, the contractors took the
work at very low prices and were soon in financial difficulties. The
commissioners made several advances to the contractors to try and keep
the work going but to no avail. In the autumn of 1835 the work was
entirely suspended. Whereupon the commissioners reported to the
provincial government that, along with the £66,000 already
expended on the canal, an additional sum of £28,000 ($112,000) was
required to finish it.132 A Bill granting this sum failed to obtain the
governor's assent.133 In the years from 1836 to 1839 the
works were maintained by means of small sums of money advanced to the
commissioners by the government in anticipation of future grants. In
1840 the commissioners were authorized to borrow a sum of £35,000
($140,000)134 and the works were resumed, but again difficulties with
the contractors resulted in little
progress, and this was the unfinished state of the canal at the time of
the union.
|
|
|
|