|
|
Canadian Historic Sites: Occasional Papers in Archaeology and History No. 8
The Canals of Canada
by John P. Heisler
Financing the Construction of Early Canals in the Canadas,
1779-1841
I
The imperial government, the provincial government and the private
company, either separately or in combination, financed canal
construction in the provinces of Upper and Lower Canada prior to 1841.
The imperial government initiated this construction. The four short
military canals with locks designed to overcome the rapids at the
Cascades and Cedars were begun in 1779 by Captain Twiss of the Royal
Engineers acting on orders from Governor Haldimand, and were completed
in 1783. Construction costs were defrayed out of the military chest.
The governor, however, knowing that these canals, though small, would
prove of great advantage to the merchants using them, considered it
unjust that the whole expense of construction operation and maintenance
should fall on the imperial government. A toll of 10 shillings,
therefore, was imposed on each batteau passing through the locks.
It was hoped that the toll collected would partly offset the costs of
maintenance. Twiss reported that £132.5.0 in tolls was collected
in 1781 and £175.15.0 in 1783 and he believed that the government
could expect to receive something like £350 annually.1
However the canals were only a partial success. The two lower ones were
damaged by ice each spring and within a decade all of them fell into
disrepair. In 1800, Colonel Gother Mann of the Royal Engineers was
authorized to make a report on these canals.2 He recommended
repair, enlargement, and the construction of a new canal at Mill Rapid
and the Cascades, and his estimate of costs was about £4,127. In
1804 the locks at Split Rock and Coteau du Lac were partly rebuilt and a
new canal about one-half mile in length with 3 locks, 6 feet in width
between the gates was constructed at the foot of the
Cascades. During the renovation and construction Captain R. H.
Bruyère of the Royal Engineers submitted detailed accounts of the work
being done to the military secretary for the information of the
commander of the forces since the expenditure for the work was met out
of the military chest which was under his control.3 In 1817
the locks on these canals were enlarged by the Royal Engineers from 6
to 12 feet in breadth and the depth of water on the sills increased from
2 feet to 3-1/2 feet for the passage of boats capable of carrying from 80
to 100 barrels of flour.4 These small military canals were
placed under the supervision of the Commissariat Department since the
principal use of them was, prior to the formation of the Rideau Canal,
for the passage of batteaux belonging to that
department.5 At the same time all repairs and other works for
maintaining them were performed by the engineer department upon
estimates submitted to the commander of the forces by whom the funds
were granted.6
II
Even before the termination of the War of 1812, the government of
Lower Canada had decided to construct a canal between Montreal and
Lachine. In January 1815 the Lower Canada House of Assembly received
from the governor a message stating that
His Majesty's Government having in contemplation the speedy
opening of a canal from the neighbourhood of the Town of Montreal to
Lachine, His Excellency the Governor-in-Chief recommends the subject
to the early consideration of the House of Assembly and that they will
grant such supply and other legislative provision as they may deem
expedient to assist in carrying into execution so important an object
and whereas the execution of such a project will greatly benefit His
Majesty's service, ameliorate the Internal Communications of this
Province and thereby tend generally to the encouragement of the
agriculture and commerce thereof.7
The legislature of Lower Canada responded to this appeal with "An Act
to grant an Aid to His Majesty to assist in opening a Canal from the
neighbourhood of Montreal to Lachine and further to provide for
facilitating the execution of the same."8 The sum of
£25,000 was appropriated for the purpose and three commissioners
were appointed and entrusted with execution of the
work.9
Captain Samuel Romilly of the Royal Engineers now studied the
project, made a survey, estimated costs and submitted his report in
1817.10 He found that the navigation of the St. Lawrence from Montreal
to Lachine, a distance of about 10 miles, was very difficult owing to
the rapid current and the shallowness of particular parts. He estimated
the cost of a canal with a depth of 3 feet of water and capable of
passing Durham boats 60 feet long, 13 feet 6 inches wide and drawing 2
feet 6 inches of water, at slightly over £46,000. This was almost
twice the figure of £25,000 appropriated for the project which was
temporarily shelved.
Meantime the imperial government had focused its attention on the
construction of the Ottawa-Rideau waterway. Nevertheless, that government
was prepared to give financial assistance should the province of Lower
Canada shoulder the burden of constructing the Lachine Canal. In June
1818 the Lords Commissioners of His Majesty's Treasury informed Earl
Bathurst, the colonial secretary, that, after considering Sir John
Sherbrooke's despatch relating to making a canal from Lachine to
Montreal, if the legislative authorities in Canada would make provision
for one-half of the expense attending the construction of the canal,
they would not object to sanctioning the payment of the remainder out of
the army extraordinaries.11 The province, however, was not
prepared to assume the burden of construction.
On 18 January 1819, the government of Lower Canada received a
petition signed by a number of leading men of the province including
several Montreal merchants, asking that they be incorporated for the
purpose of building the canal.12 A company known as "The
Company of the Proprietors of the Lachine Canal" was created with a
capital of £150,000 divided into shares of £50
each.13 The company undertook to build a canal not less than
40 feet wide at the surface of the water, 22 feet at the bottom, with
locks 110 feet long by 22 feet wide. Tolls were fixed at 12s.6d. for
small vessels under 5 tons burden and up to 30s. for vessels of over 60
tons burden. Each ton of merchandise carried paid an additional 5s. The
Crown enjoyed the right to seize the canal at any time either before or
after its completion. One of the conditions of the company's charter
was that the work should be completed within three years. The company
hired Thomas Burnett, an engineer from England, to make a survey and
estimate the cost of the work. All in all it expended £2,038 in
preliminary work, But the company soon ran into financial difficulties
notwithstanding the fact that the British government, recognizing the
value of the canal, subscribed for 600 shares while the government of
the province subscribed for 200. By 1821 only 1,780 of the original
3,000 shares of capital stock had been subscribed only
£89,000 out of a capital of £150,000.14 Therefore,
in January of that year, the company presented a petition to the
legislature outlining the financial difficulties and appealing for
certain changes in the act of incorporation.15 The company
found that a great impediment to subscriptions was
The exclusion by the thirty-first section of the Act, of the
revenues and expenses of repairs and keeping up the Canal and Branch,
which may be very heavy, from being considered a part of the capital
stock laid out and expended for making the same and thereby from
participating in the maximum of interest and profit to be allowed to the
proprietors as an inducement or bonus for risk they incur in an untried
and costly undertaking.16
The company also stated that it would be an additional stimulus to
subscriptions if tolls were permitted to be levied before the whole
canal was completed.17 Moreover, the company wanted an
extension of the three-year limit set for the completion of the work. It
also asked the provincial government to assume an additional number of
shares.18 The legislature's reply to the petition for aid was
to repeal the Act of Incorporation.19
At the same time the government of Lower Canada undertook to
construct the canal. The private shareholders of the former "Company of
the Proprietors of the Lachine Canal" were compensated for the money
which they had expended in development work while the legislature of
Lower Canada appropriated £35,000 to the construction of the
canal and granted free passage to all boats of His Majesty's service on
condition of an aid of £10,000 from the imperial
government.20 This aid was advanced by the governor and
commander-in-chief, Lord Dalhousie, from
the military chest.21 At the same time Dalhousie rightly
believed that the legislature, now fully committed to the project,
would grant further aid, if required, towards the completion of the
canal. He therefore informed the imperial government that it should
decline any further co-operation in the provincial government's
projects.22
Meantime commissioners were appointed with John Richardson as chairman
to superintend the completion of the work. They advertised for
tenders and nominated arbitrators to determine the valuation of the
lands through which the canal would run.23 At the same time
they worked out what they considered to be a practical plan for checking
and controlling expenditure, specifically the advance of money to
contractors within the limits of the agreement. The first check was the
measurement by the engineer, from time to time, of the work done, when
he certified what the contractor was entitled to receive. This
measurement could not be an accurate, precise one so long as the entire
work remained unfinished, so in his measurement the engineer kept on
the safe side. The second check was an account kept by the assistant
superintendent and overseer of the number of men employed each day by
the contractor; these were averaged at the end of each week and
inspected by the engineer. A third check, or rather security in case of
accidental inaccuracy in the estimate of work done, was the guarantees
for the contractors who were responsible for the
result.24
As work progressed the commissioners had from time to time to
approach the assembly, amid charges of extravagance, and extract more
grants from it.25 In order that the work proceed steadily despite
temporary shortages in funds, the commissioners occasionally obtained short term loans, on
their own securities, from the Bank of Montreal.26 The final
cost of £109,601 greatly exceeded the original estimate. A precedent
for imperial aid to provincial canals was established when the
British government decided to contribute £12,00027 or about
one-ninth of the final cost. The remainder, roughly £97,000, was
met by the government of Lower Canada.
III
In 1818, Captain J. F. Mann of the Royal Engineers surveyed the
Ottawa River and found the navigation impeded by rapids at Carillon and
Grenville. He therefore recommended the construction of three canals
with locks between Carillon and Grenville in order to overcome a fall in
the river of nearly 60 feet.28 The three canals
Carillon the lowest, Grenville the highest and Chute-à-Blondeau the
intermediate one were designed by the imperial authorities in 1819
on the scale of the Lachine Canal.29 The army now undertook
the canalization of the Ottawa River and construction was commenced the
same year, under the direction of the Royal Engineers, at Grenville,
midway between Montreal and the Rideau River.30 Lord
Dalhousie strongly urged the construction of this canal at an estimated
cost of £25,000 which was shortly to be increased by an additional
£25,000 to be contributed at the rate of
£8,000 per annum for three years.31 At first the
annual imperial parliamentary grant for work on the Ottawa River was
£10,000, but in 1827 this sum was increased to £15,000
annually in order to hasten the completion of the work.32
Known as the "ordnance canals," they were completed in 1833.
IV
On 10 March 1826, the Board of Ordnance requested General Gother
Mann, Inspector General of Fortifications, to select a competent officer
to be sent out to Canada to take charge of the construction of the
Rideau Canal.33 He selected Lieutenant Colonel John By of the
Royal Engineers. The Board of Ordnance stipulated that the officer
selected was to converse with Sir James Carmichael Smyth who was
experienced in the particular duties to be performed and knowledgeable
on the subject of the Rideau waterway.34 Sir James was to
draft the proper instructions for the officer selected.35
Because of the peculiar nature of the duties which the officer would be
called upon to perform, the Board of Ordnance directed that the officer
should be independent in carrying on the duty entrusted to him. He
would only make such general reports to the commanding Royal Engineer in
Canada as the custom of military service required and as desired by the
governor-in-chief, Lord Dalhousie, and the lieutenant governor of Upper
Canada.36
In his instructions to By,37 Sir James stated that in his
opinion it would be found more economical and more expeditious to build
the whole of the proposed canal by contract. The Americans had built the
entire Erie Canal that way. Should this be done the government would
avoid the formation of an expensive establishment which would otherwise
be required. Smyth then went on to say that if done by contract the
termination of the work at a fixed period could be more easily forecast.
Also, if done by contract, only three or four engineer officers and the
same number of intelligent clerks of work would be required.
The ordnance department had inserted in the colonial estimate for
the previous year, 1825, an item of £5,000 for preliminary work on
the Rideau River.38 This small item had passed the House of
Commons without attention being called to it and the ordnance department
assumed that, the item having been approved, Parliament was committed
to the Rideau Canal project which could proceed without waiting each
year for the annual building grant. This really meant that Parliament
had received no estimate of the work and had no opportunity of either
approving or disapproving of the government entering into such a large
undertaking. On 18 April 1826, Earl Bathurst, Secretary of State for
War and the Colonies, assured the Board of Ordnance that the work should
go on without waiting for the annual grant.39
As to the method of drawing the money required for construction,
Smyth suggested that the accounts should be carried on as a
supplementary Ordnance Act. The necessary sums would be drawn from the
military chest by the ordnance storekeepers. The ordnance department
would then render each year to the colonial department an account of the
sums expended and drawn out of the military chest with an estimate of
the sum required for the succeeding year.40
17 Plan of hydraulic lift lock at Peterborough, Trent Canal.
(Sessional Paper No. 20, 1910.)
|
The spring of 1827 found By busy in Montreal making arrangements with
the contractors.41 Each contract was an agreement "between
the commissary general of His Majesty's forces (in Canada) for and on
behalf of the King."42 In it "the named contractor guaranteed
to carry out the stipulated work for the unit sums noted in the
document."43 In one contract the unit prices were 4s. per
cubic yard of rock excavation and 1s. per cubic yard for earth
excavation. The contractor was
paid these prices for each of the units noted. Engineers would
measure the total amount of work completed and the quantity multiplied
by the unit price would give the total sum due to the contractor.
By toured the whole route of the canal for the first time in May
1827.44 In the next two months John Mactaggart, the chief of works, made
his initial survey of the route and submitted his report to By in
August. In it Mactaggart estimated the total cost of the work to be
£486,000.45 In the same summer Lieutenant Pooley, a young
engineer, also took a survey party over the proposed route with
instructions to prepare accurate general plans and estimates. Following
Pooley's work, By arrived at a revised estimate of £474,000.46
This estimate, it should be pointed out, was for a canal with small
locks measuring only 110 feet by 22 feet. It was not for the larger size
locks strongly recommended by Colonel By. Lord Dalhousie suggested that
the new plans and revised estimates be sent immediately to London to
ensure their arrival in time to lay before Parliament.47
Pooley was chosen for the task and left for England in November. By's
report to the Board of Ordnance strongly recommended that the size of
the locks be increased to 150 feet long by 50 feet wide with 5 feet in
depth.48
By's report with its increased estimate of £474,000 greatly
alarmed the ordnance department in London. On 2 January 1828, the Rt.
Hon. William Huskisson wrote to Lord Dalhousie that the estimate was so
alarmingly high that it had become necessary to subject the entire
proceedings to the strictest examination.49 A committee of
engineers was set up to investigate the various documents, plans and
estimates. Orders were issued to By to suspend all such operations as were not
absolutely necessary to be performed immediately. Dalhousie was
requested to assist By in prevailing upon individuals to suspend
contracts into which they may have entered but which were not yet
sanctioned by His Majesty's government.50
In its report of 22 January 1828,51 the committee of engineers
declared that it could find nothing wrong with By's plans and estimates.
The committee members were impressed by the daring plans to flood out
some of the rapids and falls with high dams. The report, however, still
did not entirely satisfy the British government. Whereupon, the Board
of Ordnance appointed a special commission of military engineers to
make a further, and what was intended to be a final, report on the
subject.52 The commission was under the chairmanship of
Lieutenant General Sir James Kempt, then lieutenant governor of Nova
Scotia, with Colonels Fanshawe and Lewis of the Royal Engineers as
members. The commission was instructed to examine personally on the spot
the plans and estimates of Colonel By. If they found the project was
practicable and that it had been designed and was being conducted
economically, then they were to authorize By to continue with the work.
Otherwise he was to be stopped. The commission was also "authorized to
approve the larger size of locks which By recommended if they agreed
with him on this point."53
Throughout the winter and spring, while the committee was actually
scrutinizing his plans and estimates, By had been carrying out more
accurate surveys and preparing further plans for the Rideau project. As
a result of this additional work he was able to submit to
the committee, when requested to do
so, an estimated cost of the different sized locks for the Rideau
Canal;54 for the Lachine lock of 108 feet long by 22 feet
wide, £544,676.2.9-1/2; for the lock of 150 feet long by 50 feet
wide with the sluices in the gates as By proposed,
£697,672.2.9-1/2; for the lock of 134 feet long by 33 feet wide
approved by the committee, £576,757.14.9-1/2.
This latter figure was reduced to £558,000 by the committee
which considered it a reasonable estimate and one which would meet
every probable contingency. The committee's decision regarding the
approved size of locks appears to have been a compromise between the two
extreme proposals of Sir James Carmichael Smyth for locks of 108 feet by
20 feet and Colonel By for locks of 150 feet by 50
feet.55
On 28 June 1828, the committee issued instructions to By authorizing
him to proceed with the work as he had planned and to build the locks
with the new dimensions of 134 feet long by 33 feet wide with the same
depth of 5 feet.56 A few days later, on 3 July, Sir James
Kempt wrote to Lord Dalhousie that the committee had gone over the whole
line of the intended navigation and inspected the work in
progress.57 Sir James then went on to say that the committee
had instructed Colonel By to proceed with the work though they were
unhappy about the amount of the estimate.58 Yet they had no
alternative but to accept it since, according to Sir James, "they could
hardly refuse their sanction to any further advance of the work and
thereby involve His Majesty's government in a certain loss for the
detention and breach of contract and at the same time sacrifice a large
portion of the expense already incurred for specific
contracts."59 They therefore
authorized By to proceed upon what the
committee members considered the most practicable means of adopting
the navigation for all probable naval and military purposes and for the
commercial uses of the upper country. The size of the new locks would
allow the passage of steamboats 30 feet wide over the paddle wheels and
for spars 108 feet long clear of opening the gates. And finally Sir
James Kempt mentioned that the committee also specified the sum to which
By's expenditure was to be confined in the year 1828.
In January 1831, Colonel By laid before Colonel Durnford, commanding
Royal Engineer in Canada, a detailed report of expenditures consisting
of 311 pages on more than 500 items.60 By showed in each case
the amount of the item in the estimate of £576,757 given the Kempt
Commission, the amount expended at the date of the report and the amount
required to complete; and when the item required an increase of
expenditure beyond the amount totalled in the estimate of £576,757
an explanation was given. In closing By wrote,
I beg in conclusion to remark, that the original Plan and Estimate
were formed from as correct data as could be obtained during the period
that the woods and swamps were uncleared, and in consequence of their
impenetrable nature; many of the surveys required has to be taken during
the severity of a Canadian winter, and when these circumstances are
taken into consideration with the additional fact that from the country
being so extremely unhealthy, nearly all my Officers, Clerks of Work and
Overseers, have suffered from repeated and severe attacks of sickness,
caught whilst in the performance of their respective duties, it will
not, I think, appear so much a matter of surprise that the Plans and
Sections have in some instances proved to be incorrect as that so few
errors have taken place.61
In this same year a select committee of the British House of Commons
was appointed to review the accounts and papers of the Rideau Canal.
After hearing witnesses who were familiar with the canal works and
searching through papers, correspondence and accounts relating to it,
the committee published a report dated 30 May 1832.62 This document was
mainly concerned with the manner in which the Rideau Canal project had
been handled by the London authorities, It contained no criticism of
the superintending engineer.
In February 1832, By submitted to the Board of Ordnance in London his
final estimate for the construction of the canal. The total now was
£715,408.63 The sum was £22,700 above what had
been voted by the imperial Parliament for that year. In addition By
calculated that "to complete the entire project with all its ancillary
defences" would require £60,615 for a total estimate of
£776,023;64 a sum exceeding by £216,023 the
estimate of £558,000 accepted and approved by the Kempt Commission
in 1828. The cost of extras found to be necessary as construction
progressed, such as the adoption of waste weirs, the enlargement of dams
and embankments following the collapse of the first dam at Hog's Back,
accounted for the substantial increase in cost apart from about
£30,000. When one considers the wretched conditions under which
the Rideau Canal was constructed, the discrepancy between approved
estimate and final cost does not seem excessive. The Lords of His
Majesty's Treasury in London, however, took a different view. On 19 May
1832 the secretary of the Board of Ordnance forwarded By's estimate to
the Treasury. Six days later a Treasury Minute was issued, part of which
stated:
My Lords have under their serious considerations the letter from
the Secretary of the Ordnance. . . . My Lords will take in their
future consideration these voluminous Accounts and Papers; but they
cannot delay expressing their opinion to the Master General and Board
of Ordnance on the conduct of Colonel By in carrying on this Work. .
. . In order, therefore, to complete the Work, Colonel By has, upon
his own responsibility, thought proper to expend no less than
£82,516. . . . It is impossible for My Lords to permit such
conduct to be pursued by any public functionary. If My Lords were to
allow any person whatsoever to expand with impunity . . . a
larger amount than that sanctioned by Parliament and by the Board, there
would be an end to all control and My Lords would feel themselves deeply
responsible to Parliament. They desire, therefore, that the Master
General and Board will take immediate steps for removing Colonel By from
any superintendence over any part of the Works for making Canal
Communication in Canada, and for placing some competent person in
charge of those works, upon whose knowledge and discretion due reliance
can be placed. . . . My Lords further desire that Colonel By may
be forthwith ordered to return to this country that he may be called
upon to afford such explanation as My Lords may consider necessary upon
this important subject. Let copies of these Papers, and this Minute be
forthwith prepared with a view to their being laid before the House of
Commons.65
This indictment was submitted officially to the House of Commons.
Colonel By was recalled. The House of Commons then appointed another
committee which heard evidence including that of Colonel By. He was
exonerated. He did not, however, receive "the honours which should
have come to the builder of the Rideau Canal."66
According to
memoranda from ordnance documents the total cost of the Rideau Canal to
the imperial government was £803,774.56 or $3,991,701.47 a
total which comprised the following items.67
|
| sterling
| Currency |
£ | s. | d. |
|
Land | 44,807 | 12 | 6-1/4 | $ 218,063.79 |
|
work done by contract | 625,545 | 6 | 5 | 3,044,320.56 |
|
Lock gates | 23,141 | 6 | 10-3/4 | 112,621.50 |
|
Pay of establishment | 110,279 | 19 | 8 | 536,695.92 |
|
| £803,744 | 5 | 6 | $3,911,701.77 |
|
V
The Welland Canal Company received its original charter in 1824.68
That charter authorized the company to issue 3,200 shares of common
stock at a par value of £12.10.0 each making a total
capitalization of £40,000. The amount was quickly subscribed by
residents in New York state who took over half the amount, and by
residents in Upper and Lower Canada who took the remainder. No attempt
was made to sell any of the stock to British investors.69
Early in the following year the Upper Canada House of Assembly passed
a resolution to lend the company £25,000 and to permit an increase
in capitalization.70 On 13 April, the company received an
amended Act of Incorporation but no accompanying financial
assistance.71 The new charter increased the authorized capital to
£200,000. It also allowed persons who had subscribed under the old
charter to withdraw and be paid their subscriptions should they
so desire. Forty persons representing a total of 170 shares took
advantage of this right. New subscriptions, however, a total of 232
being sold in Upper Canada alone, offset the withdrawals.72
Yet only eight individuals invested the £250 necessary to qualify
them for a seat on the board of directors. These eight were John Henry
Dunn, John Beverly Robinson, William Allan, Henry John Boulton, D'Arcy
Boulton, Colonel Joseph Wells, George Keefer and William Hamilton
Merritt.73 Most of these men were
persons of high social rank and politically influential. Dunn, Allan
and Wells were members of the legislative council. Allan was also
president of the government-sponsored Bank of Upper Canada. Robinson
was attorney general. He and H. J. Boulton, the solicitor general, were
leading members of the assembly. D'Arcy Boulton, father of H. J.
Boulton, was a judge of assizes.
In 1825 the board of directors petitioned the lieutenant governor of
Upper Canada for a grant of land. Maitland forwarded the petition to
Bathurst on 19 May, at the same time strongly recommending that it be
granted.74 Bathurst accepted the recommendation75
and the following year Maitland made to the company a grant of 13,000
acres of land in the township of Wainfleet. The same board meeting which
decided to petition for a grant of land also decided to reserve one-half
of the total capital stock of 8,000 shares for sale in Great
Britain to be disposed of there through the agency of the Canada
Company.76 Of the remaining 8,000 shares, 4,000 were to be
sold in the Canadas and 4,000 in New York. The board limited the amount
of the New York subscriptions because it was "anxious to preserve the
management of the Company under British influence." The Canada Company
was expected to find influential subscribers for the £100,000 of
company stock reserved for Great Britain. At the same time an agent was
sent to London with documents to explain the project in detail.
During May and June, 1825, Dunn went to New York where he not only
sold all the quota of stock reserved for that market but an additional
amount of £25,000. At the same time, he was able to sell
£25,000 of stock in the Canadas.77 This left only the
£100,000 of stock reserved for the British market to be
sold.78 However, just at the time that this was offered to
the British public, panic struck the London capital market in December,
1825, and few shares were sold. This meant that the company was deprived
of half of its capital and therefore crippled before its operations were
fully begun.
Late in 1825 Dunn informed a select committee of the assembly that
the company required assistance until the British subscriptions became
available.79 Thereupon the committee recommended that a
loan be granted and this was done on 30 January 1826.80 The company
received £25,000 repayable in three equal instalments in two,
four and six years with interest at 6 per cent payable semi-annually.
With this assistance the company continued operations during 1826. In
September of that year the Canada Company in London formed a committee
to act on behalf of the Welland Canal Company in the London money market but this
action brought no immediate relief.81 By the end of the year
the stock sold at 50 per cent discount in New York and it was clear that
the company was in serious financial difficulties.82
Meanwhile on 30 September 1826, Bathurst, the Colonial Secretary, had
stated that the British government was prepared to grant to the company
"a sum equal to one-ninth the estimated cost of construction on
condition that government stores and vessels were permitted to use the
canal without paying toll."83 As noted before, imperial aid
in the form of a grant of £12,000 or one-ninth of the estimated
cost had been given in the case of the Lachine Canal on conditions
similar to those now laid down for the Welland. The Smyth Commission,
which as we have seen visited Upper Canada in the summer of 1825, had
estimated the cost of the Welland Canal at £147,240.84 Taking this
figure as correct, Bathurst offered the sum of £16,360 sterling
to be paid in four annual instalments. However, authority to draw for
the first instalment was not immediately forthcoming and as things
eventually turned out the company never did receive this grant.
Unsuccessful in disposing of its stock in the London and New York
markets during 1826, the company, desperate for capital, turned once
again to the provincial legislature. Early in 1827 the company presented
petitions for aid, urging the provincial governments to purchase its
stock. Both of these applications were successful. In Upper Canada a
motion to purchase £50,000 of stock in the Welland Canal Company
was carried in the assembly and the whole of this subscription was made
immediately available in order that the
company might be enabled to press ahead with the work.85
However, in return for the province purchasing this stock, the company
was required to deposit with the receiver general a bond for
£20,000 to be forfeited if interest at 6 per cent were not paid
semi-annually one year after the completion of the canal to the Grand
River.86 At the same time the assembly of Lower Canada
approved a bill granting £25,000 for the purchase of Welland Canal
Company stock.87 By means of these two large subscriptions
the company's financial position was healthy during the first few months
of 1827.
18 William Hamilton Merritt (1793-1862), politician. Keenly interested
in the development of island waterways, Merrrit promoted the Welland
Canal and strongly urged the improvement of the St. Lawrence canal
system.
(Public Archives of Canada.)
|
On 10 March 1827, Dunn wrote to Lieutenant Governor Sir Peregrine
Maitland giving an account of the company's financial
position.88 At that time, of £200,000 authorized
capital stock, £93,000 had been subscribed by private
individuals. Of this sum, however, £10,000 had reverted to the
company through nonpayment of instalments. Of the remaining
£83,000, 27 per cent was still to be paid in. The company now had
available £50,000 subscribed by the government of Upper Canada
together with the British government's promise of £16,360,
Estimated total cost of the canal was now £230,000. Of this sum
£90,000 had already been spent. This left £47,000 still
required to bring the work to a successful conclusion. Since, at this
time, the imperial government had declared its intention to make money
available for public works at low interest rates, Dunn wrote that
It had suggested itself to the Directors that if His Majesty's
Government would consider the actual expenditure of £170,000 as
sufficient security to render it prudent to afford the accommodation
alluded to and would raise by loan in England the funds still wanting
say £50,000 sterling, the Directors relieved from the
uncertainty of stock being subscribed by individuals, might safely
proceed to put the Western Section of the Canal from the Welland to the
Grand River at once under contract and the certainty would be afforded
of the navigation being completed with the least possible delay; it
need scarcely be mentioned that if the remaining £57,000 stock
should be subscribed in America it would of course enable the Company
immediately to redeem the loan.89
Meanwhile, though work on the canal was progressing favourably, it
was clear that only public assistance had enabled the company to survive
as long as it had and only by the continuance of public funds could it
hope to complete its task. The hard fact was that "out of a
capitalization of £200,000 itself less than adequate
private individuals had subscribed only £83,000."90 Dunn's letter
to Maitland was forwarded to the Colonial Office on 12 March 1827.91 It
was not well received. The Treasury informed the Colonial Office that
they could not recommend Parliament "to lend any money for the
completion of the canal upon any security which the proprietors of the
company could offer."92 The Treasury went on to say, however,
that "if the provincial government were to guarantee payment of interest
on the loan and set up a sinking fund for redemption of the principal an
imperial loan might be arranged."93 Nothing was ever done
about the suggested provincial guarantee.
By 1828, the company's financial situation was desperate. It was
estimated that if no further financial assistance were forthcoming after
the end of July, the company would bankrupt. The board now decided to
send an agent to England primarily to arrange for the payment of the
imperial "one-ninth grant" and with a roving commission to sell shares or
arrange a loan wherever opportunity offered. Merritt was to be the agent
and he sailed from New York on 16 March 1828. In England he finally got
the imperial government to act and on 11 July 1828, an appropriation for
a loan of £50,000 sterling to the Welland Canal Company passed the
House of Commons.94 The loan, however, was granted instead of, not in
addition to, the "one-ninth grant" promised by Bathurst. As security for
the loan "Merritt had mortgaged the canal itself with all its property,
tolls and profits to the British government. Interest on the loan was to
be paid at 4 per cent per annum and the principal was to be repaid within
ten years. If principal and interest were not paid promptly the canal
would become government property."95 In England at this time,
Merritt also succeeded in selling all the remaining stock of the
company, or 2,467 shares, to private individuals some of them
distinguished public figures like the Duke of Wellington and Alexander
Baring.96
Until this time the company had managed to pay the interest on its
debts to the provincial government, but now the situation changed
dramatically. In November, 1828, there was a major disaster when the
slides in the Deep Cut occurred. After this incident the sum of
£54,662 was required to finish the canal for ship navigation. At
the same time something like £42,000 was needed to pay off past
indebtedness to private individuals.97
Continued deterioration characterized the company's financial
position throughout 1829. English subscriptions receded rapidly. Ellice
and Company had pledged itself to purchase £1,500 of stock and the
Canada Company had pledged itself to purchase £6,000 of
stock. When news of the Deep Cut slides reached London in July 1829,
both these companies repudiated their pledges.98 The company
now applied to the Bank of Upper Canada for a loan and a small advance
was obtained on the personal security of the directors.99
"Finally, in desperation, the board had recourse to the extraordinary
expedient of applying to the lieutenant-governor, Sir John Colborne, for
a personal loan of £10,000," which was granted.100 By
the end of the year when the canal was opened for traffic, the company
had a floating debt of £15,467 in the form of arrears to
contractors and unsettled claims for damages. Cash on hand amounted only
to £152.19.11.101
Following the completion of the canal, the directors in 1830 applied
once again to the provincial legislature for financial
assistance.102 The company now sought a loan of £25,000
in order to pay its immediate debts and to cover the cost of necessary
maintenance and repairs. It also sought to increase the capital stock to
£300,000. A majority of the assembly voted in favour of making the
loan thus bringing the investment of the provincial government in the
canal to £100,000.103 The capitalization, however, was
not enlarged. A similar petition to the legislature of Lower Canada was
a failure.104 At the same time strenuous efforts were made by
J. B. Yates, a prominent New York stockholder, to sell stock in the
United States but without success. He then went to England where he
managed to sell 1,158 shares, having only 459 still to be disposed
of.105
Once again the company applied for aid to the Upper Canada
legislature.106 A request for an additional loan of
£25,000 was referred by the assembly to a select committee which
recommended that the government should lend the company not the
£25,000 asked for but £200,000, enough to pay the loan made
by the British government as well as all previous provincial
loans.107 This recommendation the assembly rejected. Instead,
an Act was passed on 16 March 1831,108 which gave the company
a loan of £50,000 on condition that the directors should furnish
individual security that this sum would be used to complete the whole
canal including harbours and that "the government would be indemnified
against the payment of the interest and one-half of the principal." To
finance this loan the province issued debentures for a corresponding
amount which were issued directly to the canal company to be disposed of
as the directors could best arrange. "On May 11, 1831, arrangements for
a loan at 5 per cent interest were concluded with the Bank of the United
States, the provincial securities to be deposited with the bank as
collected on a dollar-for-dollar basis as and when the money was
required."109
19 Plans and sections showing the dimensions of
the smallest lock on each of the Canadian canal systems except the Trent
Canal.
(Sessional Paper No. 20, 1910.) (click
on image for a PDF version)
|
As noted previously the mortgage given to the British government
covered the whole canal and its revenues, including the large grant of
land in Wainfleet and the water-power privileges. In March, 1831,
Yates purchased all the landed property (still burdened by the mortgage
to the British government) of the company with the rights to sell or
lease the surplus water for the sum of $100,000. The canal company
received a bond for £25,000 and an understanding that
£1,500 would be paid as interest on that bond every
year.110 Yates, an alien, was unable legally to hold landed
property in his own name in Upper Canada so he formed a partnership
with his nephew, A. Y. Macdonell, and with Ogden Creighton a
partnership which came to be known as the Hydraulic Company.111
Meanwhile the Welland Canal Company faced the problem of a shortage
of cash and short-term credit.
The £50,000 grant from the provincial government could be
expended under the terms of the act only for the completion of the
canal. It was not available for the liquidation of the company's
floating debt amounting approximately to £11,000. Most of this
debt consisted of sums due the contractors for work performed and
unsettled claims for land damages.112
But sources of short-term credit were now drying up. The Bank of
Upper Canada would no longer assist the company. Early in 1832 the
directors forwarded to the Colonial Office a memorial praying that the
imperial government should give up the mortgage in so far as it related
to the land and hydraulic privileges.113 The Colonial Office
replied that in this matter Lieutenant Governor Sir John Colborne was to
use his own discretion. Treasury insisted, however, that Colborne was
not to release the company from the mortgage before first ascertaining
that ample security remained for the loan.114 Colborne
decided to do nothing.
Again the company petitioned the legislature for a loan of
£25,000 offering as security the bond given by the Hydraulic
Company. The legislature, however, refused to sanction the loan,
leaving the mortgage in the company's hands and subscribing for
£7,500 of stock. Three commissioners appointed by the legislature
were to supervise the use of this money in improving the canal. Yet the
new government subscription did not relieve the company from the
pressure of its debts. The end of 1832 found the company owing
£11,814 to contractors and other claims
amounting to £8,000. At the same time work indispensable to the
opening of navigation was estimated at £6,319.115
Once again the company attempted to raise money on the
security of the Hydraulic Company's bond. The lieutenant governor was
beseeched to release the company from the mortgage on the hydraulic
property. Colborne consulted his attorney general who advised that the
lieutenant governor should refuse to release the company from its
mortgage until the full £25,000 offered by the Hydraulic Company
was paid. Thereupon the lieutenant governor informed the board that he
would consent to the release "only if the whole £25,000 which the
company proposed to borrow on the security of the Hydraulic Company's
bond were expended on perfecting the feeder and completing the new
cutting to Lake Erie." What was most required, however, was security for
a loan to pay off the floating debt. Colborne finally granted the
release. Yates managed to obtain a loan of £25,000 which was used
to complete the new harbour on Lake Erie now named Port
Colborne.116
In 1833, Benjamin Wright, the principal canal engineer in North
America, submitted his report on the Welland Canal. He exonerated the
company from charges of waste and mismanagement.117 The
commissioners appointed by the legislature now recommended that the
canal should be made a national work. However, provincial purchase was
politically impossible until the lands and hydraulic privileges
alienated by the canal company were repurchased. Provincial purchase was
also difficult because of the attitude of the New York stockholders.
They would not surrender their title to the canal without
full payment of principal and interest.
They would much prefer not to sell if only adequate assistance was
obtained from the government. The demand for full principal and interest
removed the possibility of government purchase for the time being.
Provincial finances would not permit it.
With provincial purchase left in abeyance, the legislature passed,
on 6 March 1834, an Act118 authorizing the purchase of
£50,000 of stock, the capitalization of the company being
increased to £250,000 to accommodate the subscription. Government
representation on the board of directors was increased to three members
out of seven. The following month the assembly of Upper Canada drew up
an address to the King praying that the imperial loan of £50,000
be relinquished. The address pointed out that the province had now given
assistance by subscriptions and loans to a total of £207,500;
that three directors were appointed by the legislature; and that the
company had a right to expect, by the terms of the dispatch of 1826, a
grant of one-ninth the estimated cost of construction. The address then
went on to state that
From the amount of debt to, and the security held by His Majesty's
Government on the said Canal, the Company have been and still are
unable to obtain further loans, otherwise than from the Revenues of this
Province that the increased value of Crown Lands, which
will be produced by the completion of this work, besides the advantages
which the Mother Country will derive from the extension of commerce in
consequence thereof will in the opinion of this House more than
compensate for this expenditure of the fifty thousand pounds, which will
not exceed the one-ninth part of the cost of the said
canal.119
20 Thomas Coltrin Keefer (1821-1915), civil engineer. A leading
hydraulic engineer and first president of the Canadian Society of Civil
Engineers, Keefer was employed on the Erie, Welland, Ottawa and St.
Lawrence canals. He was also chief engineer of the Montreal Waterworks.
Taken from the Canadian Illustrated News, 26 September 1863.
(Public Archives of Canada.)
|
21 The old Sappers Bridge over the Rideau Canal,
Ottawa, as depicted by H. Cotton, 1867.
(Public Archives of Canada.)
|
The appeal was in vain. "The Colonial Secretary refused to reverse the
decision of his predecessor." To do so would, he believed, "set a bad
precedent for future assistance to important colonial
projects."120
The canal, however, still needed capital. The company now had only
two policies open to it. It could continue to rely on the provincial
government for financial aid. This meant increasing government control
and final government purchase. Or it could attempt to mobilize
sufficient capital to pay off all government loans and subscriptions and
carry on under private ownership. Both lines of policy were pursued
simultaneously. Merritt and his supporters in the Upper Canada
legislature pursued the first policy. In June, 1834, the canal company
bought back its real estate and hydraulic rights. The canal company
returned to the Hydraulic Company the bond for £25,000 originally
given in consideration for the transfer and also gave its own bond for
£17,500 payable in 50 years with interest at 6 per cent payable
semi-annually. At the same time the Hydraulic Company was permitted to
hold about 200 acres of land in Allanburg and Port
Colborne.121
Yates, acting in direct contact with financial houses in New York and
Upper Canada, now pursued the second policy of mobilizing sufficient
private capital and paying off all government loans and subscriptions
and carrying on under private ownership. By April, Yates was certain
that a loan could be raised from private sources. By September he was
ready to urge immediate action and finally in November he urged Merritt
to come to New York at once. Late in December one of Yates' staunch
Upper Canada supporters forwarded to the lieutenant governor a letter
from "certain mercantile Houses and Individuals in the City of New York"
inquiring whether he felt himself authorized to dispose of the
government interest in the canal, and if so on what
terms.122
But now political events intervened to greatly damage the company.
The legislature had appointed William Lyon Mackenzie to the board of
the company early in 1835. Mackenzie burrowed through "the company's
chaotic account books" and emerged on 21 October with "a series of
charges of fraud and defalcation on the part of the company's
officers." Merritt, a member of the assembly, succeeded in having the
matter referred to a select committee which, after prolonged inquiry,
finally emerged with a verdict of "not proven" on several accounts. But
the damage was done. Confidence in the canal was badly shaken. Yates
argued that if the government were dissatisfied with the management of
the canal, let them sell their interest in it and divest themselves of
all responsibility. He had an offer ready and the government had only to
accept. This, however, was not what Mackenzie and his followers wanted.
They were determined to make political capital out of the Welland
Canal.
During this period the company, in order to avoid complete
bankruptcy, resorted to the desperate expedient of issuing its bills as
currency. At the same time Merritt prevailed upon private individuals
"to endorse the company's notes." It was clear that if the company's
financial situation did not improve it would be impossible to keep the
canal open. "On August 6, 1836, the board decided to ask the private
stockholders for authority to open negotiations for the sale of their
interest in the canal to the provincial government."123 On 2 November a
general meeting gave the necessary permission and a memorial was presented to the
lieutenant governor praying that the province would buy out the private
shareholders.124 There also appeared on 29 November the
report of a select committee on the Welland Canal which recommended
"making the Welland Canal strictly a public work."125 At this
time investments in the canal were probably held as
follows:126
|
Shares held by private parties | £117,800 |
|
Loan and shares held by Upper Canada govt. | 275,644 |
|
Shares held by Lower Canada pvt. | 25,000 |
|
Loan by imperial government | 55,555 |
|
| £473,999 |
|
However, the legislators of Upper Canada were in no hurry to purchase
the canal. On 14 March 1837, an Act127 was passed which was
intended as a substitute for outright purchase. It dealt with the long
overdue organization of the company's finances. The capitalization was
increased to £597,300 of which the government of Upper Canada was
to hold £454,500; £209,500 to represent a consolidation of
previous loans and subscriptions, and a new subscription of
£245,000 for the permanent reconstruction of the canal with stone
locks. "The remaining lands held by the Hydraulic Company were to be
repurchased. The number of directors on the board was reduced to five so
that three government appointed directors held a
majority."128 The Act marked the end of private control.
But the Act was inoperative almost from the start. The stockmarket
crash of 1837 occurred just before the last and largest provincial
subscription could be raised. "Only £68,144 of the promised
£245,000 was actually realized. After April 1837 the province
could not sell its bonds."129 In the same year occurred the Canadian
rebellions to complete the debacle.
The three government appointed directors now informed the lieutenant
governor "that the canal could be kept open for navigation only
by incurring an annual net loss of about £14,000."130 Pessimistic
about possible future increases in traffic, they raised the question
whether it might be wiser to "let the Canal go to decay" using it as a
reservoir for water-power only rather than by continuing to pour money
into the work. Such a report represented a direct threat to the
interests of the private stockholders. If the canal was to be abandoned,
there was little hope that the private stockholders would ever receive
any return on their investment. "Their only hope lay in arranging to
withdraw their capital entirely by exchanging their shares for the
slightly less dubious security of provincial debentures."131
In March, 1839, the New York shareholders petitioned the provincial
government to buy them out.132
Two months later the legislature passed a bill133
providing for the purchase of the private stock in the canal by the
provincial government. The shareholders could now exchange their stock
if they so desired for 20-year debentures bearing interest which
increased over the years from 2 per cent to a maximum of 6 per cent. The
Bill also provided that former shareholders would receive debentures for
back interest due them once the canal tolls reached £30,000 per
annum. But by this time the state of the provincial credit was so
precarious that the lieutenant governor, Sir George Arthur, did not want
to add to the public debt for the purpose of compensating the private
stockholders until the funds required to
complete the canal had been raised. He therefore reserved the Bill
for the Queen's approval.134
However, a committee of the assembly, to which the whole matter had
been referred, advised that an address be submitted to the Queen praying
that the bill should receive the royal assent.135 A motion to
address the Crown was then carried in the legislature on 25 January
1840.136 When the first Parliament of the now united provinces met in
Kingston on 14 June 1841, the Welland Canal Compensation
Bill137 was one of the first measures introduced. It became
law on 5 July.
Yet this Act also proved to be inoperative. The debentures issued
were unsaleable at anything like their nominal value. The bonds sold in
England only at a heavy discount and both the Treasury and colonial
secretary recommended that the Act be amended. A new Act was therefore
passed in 1843138 which provided for the issue of debentures payable in
20 years, bearing interest at 5 per cent if payable in Canada, with
debentures for back interest to be issued when the canal tolls reached
an annual figure of £45,000. With this acceptable compromise, the
Welland Canal Company passed out of existence.
So far as can be ascertained the expenditure on the Welland Canal by
the time of union was as follows:139
|
Stock originally held by private parties and assumed by government | $471,200.00 |
|
Old stock held by Province of Upper Canada | 430,000.00 |
|
Loans made by Province of Upper Canada and converted into stock in 1837 | 408,000.00 |
|
New stock, Province of Upper Canada, advanced and spent up to the end of 1837 | 264,576.00 |
|
Stock held by Province of Lower Canada | 100,000.00 |
|
| $1,673,776.00 |
|
Additional expenditure prior to the union | 177,651.77 |
|
| $1,851,427.77 |
|
Sum advanced by imperial government and spent before the union | 222,220.00 |
|
Total | $2,073,647.77 |
|
VI
The difficulties experienced by the Welland Canal Company in
financing canal construction convinced the people in Upper Canada that
in future such construction should be undertaken by government.
Waterways, vital to the Canadian economy, made such demands on overseas
sources of capital that only governments could undertake such
improvements. The Cornwall Canal was a case in point. As early as 1816,
proposals to construct a canal on the St. Lawrence designed to avoid the
Long Sault Rapids at the head of Lake St. Francis had been presented to
the legislature of Upper Canada.140 Two years later a joint
commission appointed by the legislature of both provinces to report on
the water communication of the upper St. Lawrence had recommended that
an early start be made with the construction of canals on this stretch
of the river to be not less than 4 feet deep and to cost $600,000.141
Nothing was done, however, about this recommendation. Yet the subject was not allowed
to lapse. In 1826 the lieutenant governor submitted to the legislature
a report by Samuel Clowes outlining two plans, one for a canal with 8
feet depth of water and one for a 4-foot waterway.142 The
town of Brockville now took up the matter. Fearing that the completion
of the Ottawa-Rideau waterway would draw traffic away from the St.
Lawrence and thereby affect adversely the commercial life of the town,
Brockville, in 1830, undertook a preliminary survey for a canal between
Cornwall and Dickinson's Landing around the Long Sault Rapids. At the
same time the town pressured the legislature to take action in this
matter143 and this the legislature did in 1832 bypassing a
resolution approving the construction of a canal having 9 feet depth of
water.144 Commissioners were appointed the following year to
supervise the work.145 Two engineers, Benjamin Wright and
John B. Mills, were employed to make a report and the plans they
submitted for the Cornwall and Williamsburg canals involved an
estimated expenditure of £350,000.146
Work was begun on the Cornwall Canal in 1834, the only major canal
project undertaken by the province of Upper Canada before the union of
the provinces. In order to finance the project, the province floated for
the first time a series of loans in the London market. It is interesting
to note that those persons who pressed most strongly for this canal were
also involved in the Welland Canal, for they realized that the full
potentialities of the Welland could only be realized upon the complete
canalization of the St. Lawrence. Hence we find that W. H. Merritt
introduced into the Upper Canada assembly the bill that empowered J. H.
Dunn, president of the Welland Canal Company, to raise the loans in
London in 1834 and 1835. These loans were to be negotiated for the sum
required, £350,000, which was to be paid into the hands of the
receiver general and drawn by the commissioners according to the
progress of the work.147
At first construction of the Cornwall Canal proceeded briskly.
However, as noted elsewhere, the depression of 1837 combined with the
Canadian rebellions of that year made it impossible to sell Canadian
provincial securities in London. Once the sources of capital dried up,
work on the canal was suspended but not before the province had paid out
$1,448,538 on the project.148 It was resumed after the union
of the provinces and completed in 1843.
Before leaving the subject of expenditure on canal construction, a
few final remarks might be made regarding the amounts paid out by the
provincial and imperial governments for waterway improvements in the
Canadas prior to 1841.149 The Province of Lower Canada expended a total
of $889,110.58 on waterways and the Province of Upper Canada paid out
$3,430,952.57 for the same purpose. The imperial government, during
this period paid out no less than £1,069,026, a figure which
included work done on the Ottawa-Rideau waterway and contributions to
the Lachine and Welland canals.
|